Energy Projects Near You

Cressing East Solar Farm (24.9 MW)

Cressing East Solar Farm is a 24.9 MW solar farm project in Braintree, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 March 2025, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24.9 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
Braintreecouncil area

Planning timeline

DateStage
24 October 2023Application submitted
5 March 2025Planning permission granted
5 March 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
24.9 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
EDF Energy Renewables
Planning authority
Braintree
Planning application reference
23/02613/FUL
Site area
23.5 ha
Address (REPD)
W/O Lanhams Lanham Farm Road Cressing
Council area (by location)
Braintree
Time to decision
71 weeks
Contracts for Difference
AR7a
Name in REPD
Cressing East - Solar Farm
REPD reference
11235

Who decides

ApplicationsBraintreeUK
Decided applications (solar, wind, battery)3410,236
Refused3 (9%)19%
Solar refused3 of 2512%
Battery storage refused0 of 916%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Periwinkle Hall - Links Solar photovoltaic farm & Battery storagesolar farm35operational1.3
Braintree Road, Cressingbattery storage57under construction2.6
Cressing Solar Farm (Phase 2)solar farm18abandoned2.6
Cressing Solar Farm (Phase 1)solar farm5operational2.6
Cressing Farm, Witham Road Solar Farmsolar farm13.8approved, not built3.0
Park Road Solar Farmsolar farm22.5approved, not built3.9
Kentish Farm 2battery storage22.5application submitted4.6
Kentish Farm 2 Solar Farmsolar farm16.5application submitted4.6
Kentishes Solar Farmsolar farm5operational4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.864, 0.606).