Energy Projects Near You

Kentishes Solar Farm (5 MW)

Kentishes Solar Farm is a 5 MW solar farm project in Braintree, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 December 2016; the record was last updated on 18 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
18 April 2017record last updated
Braintreecouncil area

Planning timeline

DateStage
5 November 2014Application submitted
4 February 2015Refused by the planning authority
23 September 2015Appeal lodged
8 April 2016Planning permission granted
8 April 2016Appeal allowed
13 December 2016Operational
4 January 2017Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
18 April 2017
Operator or applicant
Push Energy/ NextEnergy Solar Fund (NESF)
Planning authority
Braintree
Planning application reference
14/00922/FUL
Appeal reference
APP/Z1510/W/15/3130930
Address (REPD)
Kentishes Farm, Kentish Farm Road, Stisted, Braintree
Council area (by location)
Braintree
Time to decision
74 weeks
REPD reference
1464

Who decides

ApplicationsBraintreeUK
Decided applications (solar, wind, battery)3410,236
Refused3 (9%)19%
Solar refused3 of 2512%
Battery storage refused0 of 916%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kentish Farm 2battery storage22.5application submitted0.2
Kentish Farm 2 Solar Farmsolar farm16.5application submitted0.2
Braintree Road, Cressingbattery storage57under construction3.9
Cressing East Solar Farmsolar farm24.9approved, not built4.7
Periwinkle Hall - Links Solar photovoltaic farm & Battery storagesolar farm35operational4.8
Gosfield Airfieldsolar farm12.6operational5.8
Cressing Solar Farm (Phase 1)solar farm5operational7.2
Cressing Solar Farm (Phase 2)solar farm18abandoned7.2
Cressing Farm, Witham Road Solar Farmsolar farm13.8approved, not built7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9059, 0.6024).