Energy Projects Near You

Gosfield Airfield (12.6 MW solar farm)

Gosfield Airfield is a 12.6 MW solar farm project in Braintree, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2015; the record was last updated on 19 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.6 MWsolar farm
operationalstatus in REPD
19 March 2015record last updated
Braintreecouncil area

Planning timeline

DateStage
23 December 2013Application submitted
17 April 2014Planning permission granted
1 October 2014Construction started
1 February 2015Operational

Project details

Technology
solar farm
Capacity
12.6 MW
Status (REPD)
operational
Record last updated
19 March 2015
Operator or applicant
Push Energy
Planning authority
Braintree
Planning application reference
13/01463/FUL
Address (REPD)
Gosfield Airfield, Land At Southey Green Sible, Hedingham, Essex
Council area (by location)
Braintree
Time to decision
16 weeks
REPD reference
1912

Who decides

ApplicationsBraintreeUK
Decided applications (solar, wind, battery)3410,236
Refused3 (9%)19%
Solar refused3 of 2512%
Battery storage refused0 of 916%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kentishes Solar Farmsolar farm5operational5.8
Kentish Farm 2 Solar Farmsolar farm16.5application submitted5.9
Kentish Farm 2battery storage22.5application submitted5.9
Braintree Road, Cressingbattery storage57under construction8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9558, 0.5797).