Energy Projects Near You

Solar, wind and battery projects near Halstead (CO9)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CO9 (Braintree): 3 are waiting for a planning decision, 4 approved but not yet running, 2 operational. The largest live scheme is Cutbush Farm, Belchamp St Paul (50 MW solar farm, under construction since 1 September 2025), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
3awaiting a decision
4approved, not running
2operational

Projects within 10 km of CO9

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Gosfield Airfieldsolar farmsolar farm12.6operationalupdated Mar 2015Dec 2013granted Apr 2014Mar 2015Braintree2.5
Kentishes Solar Farmsolar farmsolar farm5operationalupdated Apr 2017Nov 2014granted Apr 2016Apr 2017Braintree7.0
Kentish Farm 2battery storagebattery storage22.5application submittedupdated Aug 2025Jul 2025—Aug 2025Braintree7.1
Kentish Farm 2 Solar Farmsolar farmsolar farm16.5application submittedupdated Aug 2025Jul 2025—Aug 2025Braintree7.1
Big Deere Lodgesolarsolar6refusedupdated Apr 2014Aug 2013refused Apr 2014Apr 2014Braintree9.0
Cutbush Farm, Belchamp St Paulsolar farmsolar farm50under constructionupdated Oct 2025May 2023granted Dec 2024Oct 2025Braintree9.3
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hedingham School, Christmas Fieldrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Braintree2.3
Kentishes West, Essexbattery storagebattery storage—permission expiredupdated Feb 2020Sep 2016—Feb 2020Braintree7.1
Hole Farm, Knowl Greenrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Braintree8.1
Jack Arnold, Lancaster Wayrooftop solarrooftop solar0.2application submittedJun 2026——Braintree8.4
The Essex Golf/Leisure Club, The Airfield Earlsrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Braintree8.5

Distance from the average position of the CO9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4112066.5
Rooftop solar413000.8
Solar100010
Battery storage2100022.5

MW in pipeline: pending, approved and under-construction capacity.

How Braintree decides solar, wind and battery applications

ApplicationsBraintreeUK
Decided applications (solar, wind, battery)3410,236
Refused3 (9%)19%
Solar refused3 of 2512%
Battery storage refused0 of 916%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Braintree

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.