Solar, wind and battery projects near Bures (CO8)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CO8 (Braintree): 3 are waiting for a planning decision, 9 approved but not yet running. The largest live scheme is Boxted (20 MW solar farm, application submitted on 2 November 2023, no decision recorded; REPD status may be out of date), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CO8
Projects of 1 MW and more (3)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Rogers Farmsolar farm | solar farm | 15 | refused on appealupdated Jun 2016 | Sep 2013 | refused Feb 2014 | Jun 2016 | Babergh | 7.8 |
| Lodge Farm, Boxted Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | Colchester | 8.6 |
| Boxtedsolar farm | solar farm | 20 | application submitted may be out of dateupdated Nov 2023 | Nov 2023 | — | Nov 2023 | Colchester | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Fordham Road, Wormingfordrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2025 | Jul 2025 | granted Sep 2025 | Aug 2025 | Colchester | 4.5 |
| Greenacres, Packards Lanerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Jan 2025 | Feb 2025 | Colchester | 4.9 |
| Plummers Road, Fordhamsolar farm | solar farm | 0.3 | application withdrawnupdated Jun 2023 | Mar 2023 | — | Jun 2023 | Colchester | 5.7 |
| Alexandra Road, Windham Roadbattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Babergh | 7.7 |
| Curzon Road, Chilton Industrial Estate - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Apr 2025 | Apr 2025 | Babergh | 7.7 |
| Brundon Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Babergh | 7.9 |
| Northern Road, Chilton Industrial Estate Solar Parksolar farm | solar farm | 0.7 | approved, not built may be out of dateupdated Jun 2022 | Jun 2022 | granted Aug 2022 | Jun 2022 | Babergh | 8.2 |
| Church Field Road, Waldingfield Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application submitted | Apr 2026 | — | — | Babergh | 8.5 |
| Woodhall Business Park - Micro Energy Storage Systembattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Babergh | 9.0 |
| The Essex Golf/Leisure Club, The Airfield Earlsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | Braintree | 9.0 |
| Jack Arnold, Lancaster Wayrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — | Braintree | 9.3 |
Distance from the average position of the CO8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 1 | 1 | 0 | 1 | 20.7 |
| Rooftop solar | 6 | 1 | 5 | 0 | 0 | 2.3 |
| Battery storage | 4 | 1 | 3 | 0 | 0 | 0.8 |
MW in pipeline: pending, approved and under-construction capacity.
How Braintree decides solar, wind and battery applications
| Applications | Braintree | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 34 | 10,236 |
| Refused | 3 (9%) | 19% |
| Solar refused | 3 of 25 | 12% |
| Battery storage refused | 0 of 9 | 16% |
| Median time from submission to decision | 15.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CO8, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.