Energy Projects Near You

Boxted (20 MW solar farm)

Boxted is a 20 MW solar farm project in Colchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 2 November 2023, no decision recorded; the record was last updated on 13 November 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
application submittedmay be out of datestatus in REPD
13 November 2023record last updated
Colchestercouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
2 November 2023Application submitted

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
application submitted
Record last updated
13 November 2023
Operator or applicant
RES Limited
Planning authority
Colchester
Planning application reference
DC/23/05127
Site area
43.7 ha
Address (REPD)
W/O Boxted, Bury St Edmunds
Council area (by location)
Colchester
Name in REPD
Boxted - Solar Panels
REPD reference
12993

Who decides

ApplicationsColchesterUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused1 of 1912%
Battery storage refused1 of 516%
Median time from submission to decision13.3 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Boxted Airfieldsolar farm18.8operational2.5
Stephenson Road - Urban Reserve Flexible Energy Facilitybattery storage6approved, not built4.7
Chancery Farm (Ardleigh)solar farm11.9operational8.1
Ardleigh Road, Little Bromleybattery storage50approved, not built8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9611, 0.9084).