Energy Projects Near You

Ardleigh Road, Little Bromley (50 MW battery storage)

Ardleigh Road, Little Bromley is a 50 MW battery storage project in Tendring, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 September 2022, not yet built; the record was last updated on 1 November 2022. REPD also records that the planning permission expired on 28 September 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtmay be out of datestatus in REPD
1 November 2022record last updated
Tendringcouncil area

REPD also records that the planning permission expired on 28 September 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
15 December 2021Application submitted
28 September 2022Planning permission granted
28 September 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
1 November 2022
Operator or applicant
Lawford Power Limited
Planning authority
Tendring
Planning application reference
21/02070/FUL
Address (REPD)
Adj Lawford Grid Substation Ardleigh Road Little Bromley
Council area (by location)
Tendring
Time to decision
41 weeks
Name in REPD
Ardleigh Road, Little Bromley - Battery Energy Storage
REPD reference
10302

Who decides

ApplicationsTendringUK
Decided applications (solar, wind, battery)2610,236
Refused10 (38%)19%
Solar refused5 of 1912%
Onshore wind refused4 of 445%
Battery storage refused1 of 316%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chancery Farm (Ardleigh)solar farm11.9operational1.7
Land North of Horsley Cross Solar Farm & Battery Energy Storagesolar farm34application submitted4.8
Stephenson Road - Urban Reserve Flexible Energy Facilitybattery storage6approved, not built5.8
Bluegates Solar Parksolar farm10.5operational6.3
Boxted Airfieldsolar farm18.8operational6.6
Wix Lodgesolar farm18.7operational7.4
Boxtedsolar farm20application submitted8.9
Burnt Ash Farmsolar farm13.5refused on appeal9.0
Holmwood Solar Farmsolar farm19refused on appeal9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9167, 1.0166).