Bluegates Solar Park (10.5 MW)

Bluegates Solar Park is a 10.5 MW solar farm project in Tendring, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 January 2015; the record was last updated on 7 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.5 MWsolar farm
operationalstatus in REPD
7 May 2015record last updated
Tendringcouncil area

Planning timeline

DateStage
4 April 2014Application submitted
4 July 2014Planning permission granted
1 October 2014Construction started
30 January 2015Operational

Project details

Technology
solar farm
Capacity
10.5 MW
Status (REPD)
operational
Record last updated
7 May 2015
Operator or applicant
Edgar Middleton
Planning authority
Colchester
Planning application reference
14/00352/FUL
Address (REPD)
Blue Gates Farm Colchester Main Road Alresford
Council area (by location)
Tendring
Time to decision
13 weeks
REPD reference
5125

Who decides

ApplicationsColchesterUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused1 of 1912%
Battery storage refused1 of 516%
Median time from submission to decision13.3 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Holmwood Solar Farmsolar farm19refused on appeal3.8
Chancery Farm (Ardleigh)solar farm11.9operational5.6
Ardleigh Road, Little Bromleybattery storage50approved, not built6.3
Langenhoe Solar Farmsolar farm21.3operational7.0
Chisbon Solar Farm (Frowick Lane)solar farm13operational7.1
Hartley Wood Farm Solar Farmsolar farm22.5approved, not built8.3
Land North of Horsley Cross Solar Farm & Battery Energy Storagesolar farm34application submitted8.3
Stephenson Road - Urban Reserve Flexible Energy Facilitybattery storage6approved, not built8.4
Clay Lane, St Osyth Solar Farmsolar farm20approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8607, 1.005).