Energy Projects Near You

Holmwood Solar Farm (19 MW)

Holmwood Solar Farm is a 19 MW solar farm project in Colchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 13 January 2016; the record was last updated on 5 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19 MWsolar farm
refused on appealstatus in REPD
5 February 2016record last updated
Colchestercouncil area

Planning timeline

DateStage
20 March 2014Application submitted
6 February 2015Refused by the planning authority
12 June 2015Appeal lodged
13 January 2016Appeal refused

Project details

Technology
solar farm
Capacity
19 MW
Status (REPD)
refused on appeal
Record last updated
5 February 2016
Operator or applicant
Holmwood Solar
Planning authority
Colchester
Planning application reference
142446
Appeal reference
APP/A1530/W/15/3013657
Address (REPD)
Land South of Holmwood Farm, Brook Hall Road, Fingringhoe, Colchester
Council area (by location)
Colchester
Time to decision
46 weeks
REPD reference
1921

Who decides

ApplicationsColchesterUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused1 of 1912%
Battery storage refused1 of 516%
Median time from submission to decision13.3 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Langenhoe Solar Farmsolar farm21.3operational3.3
Bluegates Solar Parksolar farm10.5operational3.8
Layer Farm Solar Farmsolar farm49operational7.8
Chancery Farm (Ardleigh)solar farm11.9operational8.1
Chisbon Solar Farm (Frowick Lane)solar farm13operational9.1
Stephenson Road - Urban Reserve Flexible Energy Facilitybattery storage6approved, not built9.1
Ardleigh Road, Little Bromleybattery storage50approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8409, 0.9592).