Layer Farm Solar Farm (49 MW)

Layer Farm Solar Farm is a 49 MW solar farm project in Colchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2024; the record was last updated on 30 October 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWsolar farm
operationalstatus in REPD
30 October 2024record last updated
Colchestercouncil area

Planning timeline

DateStage
4 December 2020Application submitted
13 January 2022Planning permission granted
1 October 2024Operational

Project details

Technology
solar farm
Capacity
49 MW
Status (REPD)
operational
Record last updated
30 October 2024
Operator or applicant
Layer Solar Farm Limited
Planning authority
Colchester
Planning application reference
202695
Site area
96.8 ha
Address (REPD)
Land west of Layer de la Haye
Council area (by location)
Colchester
Time to decision
58 weeks
Contracts for Difference
AR4
Name in REPD
Layer Farm - Solar Farm
REPD reference
8251

Who decides

ApplicationsColchesterUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused1 of 1912%
Battery storage refused1 of 516%
Median time from submission to decision13.3 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land Adjacent Claypits Farm (a)solar farm5operational2.9
Birch Solar Farm & Battery Storagesolar farm40operational3.5
Birch Airfieldsolar farm5.6operational4.1
Langenhoe Solar Farmsolar farm21.3operational7.2
Wilkin And Sons, Factory Hill Solar Farmsolar farm6.2operational7.8
Holmwood Solar Farmsolar farm19refused on appeal7.8
Highfields Farm (Colchester)solar farm12.2operational9.1
Skye Green Solar Farmsolar farm15approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8471, 0.8463).