Energy Projects Near You

Land Adjacent Claypits Farm (a) (5 MW solar farm)

Land Adjacent Claypits Farm (a) is a 5 MW solar farm project in Colchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 December 2015; the record was last updated on 24 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
24 August 2016record last updated
Colchestercouncil area

Planning timeline

DateStage
27 March 2015Application submitted
30 June 2015Planning permission granted
22 October 2015Construction started
23 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
24 August 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Colchester
Planning application reference
150614
Address (REPD)
Land Adjacent Claypits Farm, Maldon Road, Birch, Colchester, Essex
Council area (by location)
Colchester
Time to decision
14 weeks
REPD reference
5182

Who decides

ApplicationsColchesterUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused1 of 1912%
Battery storage refused1 of 516%
Median time from submission to decision13.3 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Birch Airfieldsolar farm5.6operational1.3
Birch Solar Farm & Battery Storagesolar farm40operational1.8
Layer Farm Solar Farmsolar farm49operational2.9
Wilkin And Sons, Factory Hill Solar Farmsolar farm6.2operational5.4
Highfields Farm (Colchester)solar farm12.2operational6.2
Skye Green Solar Farmsolar farm15approved, not built7.1
Langenhoe Solar Farmsolar farm21.3operational9.6
Beckingham Roadsolar farm10.7refused9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8433, 0.805).