Energy Projects Near You

Birch Solar Farm & Battery Storage (40 MW)

Birch Solar Farm & Battery Storage is a 40 MW solar farm project in Colchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational; the record was last updated on 16 May 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
operationalstatus in REPD
16 May 2023record last updated
Colchestercouncil area

Planning timeline

DateStage
22 August 2022Application submitted
20 March 2023Planning permission granted

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
operational
Record last updated
16 May 2023
Operator or applicant
Low Carbon Solar Park 22 Limited
Planning authority
Colchester
Planning application reference
222151
Site area
87.0 ha
Address (REPD)
NW/O Hardys Green, Birch Colchester
Council area (by location)
Colchester
Time to decision
30 weeks
Contracts for Difference
AR5
REPD reference
12101

The scheme also includes battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsColchesterUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused1 of 1912%
Battery storage refused1 of 516%
Median time from submission to decision13.3 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land Adjacent Claypits Farm (a)solar farm5operational1.8
Birch Airfieldsolar farm5.6operational2.6
Layer Farm Solar Farmsolar farm49operational3.5
Skye Green Solar Farmsolar farm15approved, not built6.4
Wilkin And Sons, Factory Hill Solar Farmsolar farm6.2operational6.6
Highfields Farm (Colchester)solar farm12.2operational6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8593, 0.7993).