Wilkin And Sons, Factory Hill Solar Farm (6.2 MW)

Wilkin And Sons, Factory Hill Solar Farm is a 6.2 MW solar farm project in Colchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2023; the record was last updated on 21 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWsolar farm
operationalstatus in REPD
21 March 2024record last updated
Colchestercouncil area

Planning timeline

DateStage
30 December 2022Application submitted
1 January 2023Operational
6 June 2023Planning permission granted

Project details

Technology
solar farm
Capacity
6.2 MW
Status (REPD)
operational
Record last updated
21 March 2024
Operator or applicant
Wilkin & Sons Limited
Planning authority
Colchester
Planning application reference
223177
Site area
10.6 ha
Address (REPD)
Wilkin And Sons Limited, Factory Hill, Tiptree, Colchester
Council area (by location)
Colchester
Time to decision
23 weeks
Name in REPD
Wilkin And Sons, Factory Hill - Solar Farm
REPD reference
13025

Who decides

ApplicationsColchesterUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused1 of 1912%
Battery storage refused1 of 516%
Median time from submission to decision13.3 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Highfields Farm (Colchester)solar farm12.2operational3.1
Birch Airfieldsolar farm5.6operational4.1
Beckingham Roadsolar farm10.7refused4.5
Land Adjacent Claypits Farm (a)solar farm5operational5.4
Little Braxted Solar Parksolar farm15appeal withdrawn6.4
Birch Solar Farm & Battery Storagesolar farm40operational6.6
Skye Green Solar Farmsolar farm15approved, not built6.9
Layer Farm Solar Farmsolar farm49operational7.8
Park Road Solar Farmsolar farm22.5approved, not built8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.807, 0.7538).