Wilkin And Sons, Factory Hill Solar Farm (6.2 MW)
Wilkin And Sons, Factory Hill Solar Farm is a 6.2 MW solar farm project in Colchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2023; the record was last updated on 21 March 2024.
6.2 MWsolar farm
operationalstatus in REPD
21 March 2024record last updated
Colchestercouncil area
Planning timeline
| Date | Stage |
|---|---|
| 30 December 2022 | Application submitted |
| 1 January 2023 | Operational |
| 6 June 2023 | Planning permission granted |
Project details
- Technology
- solar farm
- Capacity
- 6.2 MW
- Status (REPD)
- operational
- Record last updated
- 21 March 2024
- Operator or applicant
- Wilkin & Sons Limited
- Planning authority
- Colchester
- Planning application reference
- 223177
- Site area
- 10.6 ha
- Address (REPD)
- Wilkin And Sons Limited, Factory Hill, Tiptree, Colchester
- Council area (by location)
- Colchester
- Time to decision
- 23 weeks
- Name in REPD
- Wilkin And Sons, Factory Hill - Solar Farm
- REPD reference
- 13025
Who decides
| Applications | Colchester | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 24 | 10,236 |
| Refused | 2 (8%) | 19% |
| Solar refused | 1 of 19 | 12% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 13.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Highfields Farm (Colchester) | solar farm | 12.2 | operational | 3.1 |
| Birch Airfield | solar farm | 5.6 | operational | 4.1 |
| Beckingham Road | solar farm | 10.7 | refused | 4.5 |
| Land Adjacent Claypits Farm (a) | solar farm | 5 | operational | 5.4 |
| Little Braxted Solar Park | solar farm | 15 | appeal withdrawn | 6.4 |
| Birch Solar Farm & Battery Storage | solar farm | 40 | operational | 6.6 |
| Skye Green Solar Farm | solar farm | 15 | approved, not built | 6.9 |
| Layer Farm Solar Farm | solar farm | 49 | operational | 7.8 |
| Park Road Solar Farm | solar farm | 22.5 | approved, not built | 8.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.807, 0.7538).