Solar, wind and battery projects near Witham (CM8)
30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CM8 (Braintree): 2 are waiting for a planning decision, 17 approved but not yet running, 7 operational. The largest live scheme is Longfield (500 MW solar farm, approved on 26 June 2023, not yet built), 6.8 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Gunfleet Sands - (Demo) Extension (12 MW, operational), 39.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CM8
Projects of 1 MW and more (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Little Braxted Solar Parksolar farm | solar farm | 15 | appeal withdrawnupdated Jan 2014 | Jan 2013 | refused Jun 2013 | Jan 2014 | Maldon | 1.7 |
| Park Road Solar Farmsolar farm | solar farm | 22.5 | approved, not builtupdated Mar 2026 | Jan 2022 | granted Dec 2023 | Mar 2026 | Braintree | 3.6 |
| Cressing Farm, Witham Road Solar Farmsolar farm | solar farm | 13.8 | approved, not builtupdated Feb 2026 | Jan 2025 | granted Jun 2025 | Feb 2026 | Braintree | 3.9 |
| Cressing Solar Farm (Phase 2)solar farm | solar farm | 18 | abandonedupdated Aug 2018 | Jul 2015 | granted Nov 2015 | Aug 2018 | Braintree | 4.6 |
| Cressing Solar Farm (Phase 1)solar farm | solar farm | 5 | operationalupdated Apr 2017 | Jul 2015 | granted Nov 2015 | Apr 2017 | Braintree | 4.6 |
| Beckingham Roadsolar farm | solar farm | 10.7 | refusedupdated Sep 2014 | May 2014 | refused Jul 2014 | Sep 2014 | Maldon | 5.8 |
| Highfields Farm (Colchester)solar farm | solar farm | 12.2 | operationalupdated Sep 2014 | Dec 2012 | granted Sep 2013 | Sep 2014 | Colchester | 6.0 |
| Highfields Farm (Braintree)solar farm | solar farm | 2.8 | operationalupdated Sep 2014 | Dec 2012 | granted Sep 2013 | Sep 2014 | Colchester | 6.0 |
| Periwinkle Hall - Links Solar photovoltaic farm & Battery storagesolar farm | solar farm | 35 | operationalupdated Oct 2024 | Jun 2021 | granted Dec 2021 | Oct 2024 | Braintree | 6.6 |
| Cressing East Solar Farmsolar farm | solar farm | 24.9 | approved, not builtupdated Feb 2026 | Oct 2023 | granted Mar 2025 | Feb 2026 | Braintree | 6.8 |
| Longfieldsolar farm | solar farm | 500 | approved, not builtupdated Jun 2023 | Feb 2022 | granted Jun 2023 | Jun 2023 | Chelmsford | 6.8 |
| Skye Green Solar Farmsolar farm | solar farm | 15 | approved, not builtupdated Feb 2026 | Dec 2024 | granted Apr 2025 | Feb 2026 | Braintree | 7.7 |
| Wilkin And Sons, Factory Hill Solar Farmsolar farm | solar farm | 6.2 | operationalupdated Mar 2024 | Dec 2022 | granted Jun 2023 | Mar 2024 | Colchester | 8.0 |
| Braintree Road, Cressingbattery storage | battery storage | 57 | under constructionupdated Mar 2026 | Aug 2022 | granted Sep 2023 | Mar 2026 | Braintree | 8.9 |
| Maldon Hallbattery storage | battery storage | 40 | approved, not built may be out of dateupdated Dec 2021 | Sep 2017 | granted May 2019 | Dec 2021 | Maldon | 8.9 |
| Slamseys Energy Storagebattery storage | battery storage | 10 | under constructionupdated Jan 2020 | Jul 2017 | granted Sep 2017 | Jan 2020 | Braintree | 9.2 |
Smaller schemes under 1 MW, mostly rooftop solar (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Morrisons Withamrooftop solar | rooftop solar | 0.2 | operationalupdated Nov 2021 | Nov 2021 | granted Mar 2023 | Nov 2021 | Braintree | 0.4 |
| Cego Limited, Crittall Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | Braintree | 0.8 |
| Spinks Lane - Micro Energy Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Braintree | 1.2 |
| Verge By Ricksones School, Rickstones Road - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | May 2025 | granted Jul 2025 | Nov 2025 | Braintree | 1.5 |
| Colemans Farmsolar farm | solar farm | 0.3 | application submitted may be out of dateupdated May 2019 | May 2019 | — | May 2019 | Braintree | 1.5 |
| Howbridge Junior School, Dengie Closerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Braintree | 1.6 |
| Motus Trucks and Vans, Griggs Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Feb 2023 | Feb 2023 | Braintree | 1.7 |
| Sewage Pumping Station, Worlds End Lanebattery storage | battery storage | 0.2 | application submittedupdated Sep 2024 | Sep 2024 | — | Sep 2024 | Braintree | 6.0 |
| Periwinkle Hall - Links Solar photovoltaic farm & Battery storagebattery storage | battery storage | — | operationalupdated Oct 2024 | Jun 2021 | granted Dec 2021 | Oct 2024 | Braintree | 6.6 |
| Longfieldbattery storage | battery storage | — | approved, not builtupdated Jun 2023 | Feb 2022 | granted Jun 2023 | Jun 2023 | Chelmsford | 6.8 |
| Church Road Tescorooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2020 | Oct 2019 | granted Nov 2019 | Jun 2020 | Colchester | 7.9 |
| Sub Zero And Wolf Limited, The Streetrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 | Maldon | 8.1 |
| Braintree Village, Charter Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jul 2025 | May 2025 | granted Jun 2025 | Jul 2025 | Braintree | 8.4 |
| London Road, Great Notley - Micro Energy Storagebattery storage | battery storage | 0.2 | application withdrawnupdated Nov 2025 | May 2025 | — | Nov 2025 | Braintree | 9.3 |
Distance from the average position of the CM8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 14 | 1 | 5 | 5 | 1 | 576 |
| Rooftop solar | 7 | 0 | 6 | 1 | 0 | 1.4 |
| Battery storage | 9 | 1 | 6 | 1 | 0 | 108 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Gunfleet Sands - (Demo) Extension | 12 | operationalupdated Nov 2017 | 39.9 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Braintree decides solar, wind and battery applications
| Applications | Braintree | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 34 | 10,236 |
| Refused | 3 (9%) | 19% |
| Solar refused | 3 of 25 | 12% |
| Battery storage refused | 0 of 9 | 16% |
| Median time from submission to decision | 15.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CM8, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.