Slamseys Energy Storage (10 MW)

Slamseys Energy Storage is a 10 MW battery storage project in Braintree, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 13 January 2020; the record was last updated on 20 January 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
under constructionstatus in REPD
20 January 2020record last updated
Braintreecouncil area

Planning timeline

DateStage
6 July 2017Application submitted
15 September 2017Planning permission granted
13 January 2020Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
10 MW
Status (REPD)
under construction
Record last updated
20 January 2020
Operator or applicant
Gridserve Energy Storage
Planning authority
Braintree
Planning application reference
17/01235/FUL
Address (REPD)
Land North Of Slamseys Farm, Blackley Lane, Great Notley, Essex
Council area (by location)
Braintree
Time to decision
10 weeks
REPD reference
7000

Who decides

ApplicationsBraintreeUK
Decided applications (solar, wind, battery)3410,236
Refused3 (9%)19%
Solar refused3 of 2512%
Battery storage refused0 of 916%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Felsted School Road Solar Photovoltaic Farm & Battery storagesolar farm49.9approved, not built1.2
Drapers Farm Solar Parksolar farm6operational1.8
Braintree Road, Cressingbattery storage57under construction4.4
Cressing Solar Farm (Phase 2)solar farm18abandoned5.4
Cressing Solar Farm (Phase 1)solar farm5operational5.4
Cressing East Solar Farmsolar farm24.9approved, not built5.9
Cressing Farm, Witham Road Solar Farmsolar farm13.8approved, not built6.1
Periwinkle Hall - Links Solar photovoltaic farm & Battery storagesolar farm35operational7.1
Longfieldsolar farm500approved, not built7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8508, 0.5235).