Energy Projects Near You

Longfield (500 MW solar farm)

Longfield is a 500 MW solar farm project in Chelmsford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 June 2023, not yet built; the record was last updated on 26 June 2023. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010118).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWsolar farm
approved, not builtstatus in REPD
26 June 2023record last updated
Chelmsfordcouncil area

Planning timeline

DateStage
28 February 2022Application submitted
26 June 2023Development consent granted (Secretary of State)
26 June 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
500 MW
Status (REPD)
approved, not built
Record last updated
26 June 2023
Operator or applicant
Longfield Solar Energy Farm Limited (part of EDF Renwables)
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010118
Site area
453.0 ha
Address (REPD)
north east of Chelmsford and North of the A12 between Boreham and Hatfield Peverel
Council area (by location)
Chelmsford
Time to decision
69 weeks
Contracts for Difference
AR6
REPD reference
8162

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Official project record at the Planning Inspectorate (EN010118)

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010118). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
St Cleres Hall Pit Solar Arraysolar farm25approved, not built6.9
Cressing Farm, Witham Road Solar Farmsolar farm13.8approved, not built7.4
Cressing Solar Farm (Phase 2)solar farm18abandoned7.5
Cressing Solar Farm (Phase 1)solar farm5operational7.5
Slamseys Energy Storagebattery storage10under construction7.7
Little Braxted Solar Parksolar farm15appeal withdrawn8.3
Felsted School Road Solar Photovoltaic Farm & Battery storagesolar farm49.9approved, not built8.6
Drapers Farm Solar Parksolar farm6operational8.7
Park Road Solar Farmsolar farm22.5approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7832, 0.545).