Energy Projects Near You

Cressing Farm, Witham Road Solar Farm (13.8 MW)

Cressing Farm, Witham Road Solar Farm is a 13.8 MW solar farm project in Braintree, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 June 2025, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Braintreecouncil area

Planning timeline

DateStage
7 January 2025Application submitted
6 June 2025Planning permission granted
6 June 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
13.8 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Eden Renewables
Planning authority
Braintree
Planning application reference
24/02673/FUL
Site area
40.8 ha
Address (REPD)
Cressing Farm Witham Road Cressing
Council area (by location)
Braintree
Time to decision
21 weeks
Contracts for Difference
AR7a
Name in REPD
Cressing Farm, Witham Road - Solar Farm
REPD reference
12123

Who decides

ApplicationsBraintreeUK
Decided applications (solar, wind, battery)3410,236
Refused3 (9%)19%
Solar refused3 of 2512%
Battery storage refused0 of 916%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cressing Solar Farm (Phase 2)solar farm18abandoned0.7
Cressing Solar Farm (Phase 1)solar farm5operational0.7
Park Road Solar Farmsolar farm22.5approved, not built2.4
Cressing East Solar Farmsolar farm24.9approved, not built3.0
Periwinkle Hall - Links Solar photovoltaic farm & Battery storagesolar farm35operational3.3
Braintree Road, Cressingbattery storage57under construction5.0
Little Braxted Solar Parksolar farm15appeal withdrawn5.3
Slamseys Energy Storagebattery storage10under construction6.1
Skye Green Solar Farmsolar farm15approved, not built7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8369, 0.6095).