Little Braxted Solar Park (15 MW)

Little Braxted Solar Park is a 15 MW solar farm project in Maldon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 20 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
appeal withdrawnstatus in REPD
20 January 2014record last updated
Maldoncouncil area

Planning timeline

DateStage
14 January 2013Application submitted
14 June 2013Refused by the planning authority
8 August 2013Appeal withdrawn

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
appeal withdrawn
Record last updated
20 January 2014
Operator or applicant
Lightsource Renewable Energy
Planning authority
Maldon
Planning application reference
13/00036/FUL
Address (REPD)
Land South Of Little Braxted Hall, Witham Road Little Braxted, Essex
Council area (by location)
Maldon
Time to decision
22 weeks
REPD reference
1615

Who decides

ApplicationsMaldonUK
Decided applications (solar, wind, battery)2010,236
Refused11 (55%)19%
Solar refused7 of 1312%
Onshore wind refused2 of 345%
Battery storage refused2 of 416%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Beckingham Roadsolar farm10.7refused4.2
Park Road Solar Farmsolar farm22.5approved, not built4.2
Highfields Farm (Colchester)solar farm12.2operational4.8
Cressing Farm, Witham Road Solar Farmsolar farm13.8approved, not built5.3
Cressing Solar Farm (Phase 1)solar farm5operational6.0
Cressing Solar Farm (Phase 2)solar farm18abandoned6.0
Wilkin And Sons, Factory Hill Solar Farmsolar farm6.2operational6.4
Skye Green Solar Farmsolar farm15approved, not built7.3
Periwinkle Hall - Links Solar photovoltaic farm & Battery storagesolar farm35operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8017, 0.6612).