Energy Projects Near You

Renewable energy projects in Maldon

18 solar, wind or battery projects of 150 kW or more are located in Maldon (REPD, July 2026 extract): 1 pending, 7 approved but not running, 5 operational and 3 refused. The council refused 11 of 20 decided applications (55%; UK 19%), with a median 20 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18projects in the council area
1awaiting a decision
7approved, not running
55%of decisions refused

How Maldon decides

ApplicationsMaldonUK
Decided applications (solar, wind, battery)2010,236
Refused11 (55%)19%
Solar refused7 of 1312%
Onshore wind refused2 of 345%
Battery storage refused2 of 416%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Projects in Maldon

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Maldon Hallbattery storagebattery storage40approved, not built may be out of dateupdated Dec 2021Sep 2017granted May 2019Dec 2021
Marshes Farmsolar farmsolar farm25.5approved, not builtupdated Nov 2025Dec 2024granted Sep 2025Nov 2025
Maldon Wycke Solar Farmsolar farmsolar farm25operationalupdated Oct 2024Feb 2022granted Aug 2022Oct 2024
Prentice’s Farm- Solar Farmsolar farmsolar farm21approved, not builtupdated Feb 2026Apr 2024granted Sep 2024Feb 2026
Middlewick wind farmwind farmwind farm20.7operationalupdated Jan 2015Jan 2010granted May 2011Jan 2015
Bradwell Wind Farm (Repower)wind farmwind farm20operationalupdated Jan 2014Mar 2006granted Jul 2006Jan 2014
Dengiesolar farmsolar farm19approved, not builtupdated May 2024Dec 2023granted May 2024May 2024
Turncole Wind Farmwind farmwind farm17.5operationalupdated Dec 2016Jun 2011granted Feb 2014Dec 2016
Little Braxted Solar Parksolar farmsolar farm15appeal withdrawnupdated Jan 2014Jan 2013refused Jun 2013Jan 2014
Beckingham Roadsolar farmsolar farm10.7refusedupdated Sep 2014May 2014refused Jul 2014Sep 2014
Jackletts Farmsolar farmsolar farm10refusedupdated Jul 2014Jul 2013refused Oct 2013Jul 2014
Wick Farm (Burnham on Crouch)solar farmsolar farm5operationalupdated Aug 2017Sep 2014granted Jan 2015Aug 2017
Corporation Farmsolar farmsolar farm5abandonedupdated Mar 2019Aug 2015granted Apr 2017Mar 2019
Land West Of Flambirds Farmsolar farmsolar farm5refusedupdated Dec 2015Aug 2015refused Nov 2015Dec 2015
Dengiebattery storagebattery storage5approved, not builtupdated May 2024Dec 2023granted May 2024May 2024
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Sub Zero And Wolf Limited, The Streetrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Nov 2022Aug 2022granted Oct 2022Nov 2022
Marshes Farmbattery storagebattery storage—approved, not builtupdated Nov 2025Dec 2024granted Sep 2025Nov 2025
Dengie Crops Limited, Hall Roadwind turbinewind turbine—application submittedupdated Jan 2026Oct 2025—Jan 2026

Postcode districts in Maldon

DistrictProjects within 10 kmPendingApprovedOperational
CM010244
CM922196

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Maldon by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.