Energy Projects Near You

Turncole Wind Farm (17.5 MW)

Turncole Wind Farm is a 17.5 MW wind farm project in Maldon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 December 2016; the record was last updated on 22 December 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.5 MWwind farm
operationalstatus in REPD
22 December 2016record last updated
Maldoncouncil area

Planning timeline

DateStage
30 June 2011Application submitted
25 October 2011Refused by the planning authority
14 February 2014Planning permission granted
14 February 2014Appeal allowed
31 October 2015Construction started
22 December 2016Operational

Project details

Technology
wind farm
Capacity
17.5 MW
Status (REPD)
operational
Record last updated
22 December 2016
Operator or applicant
RES/ Aviva
Planning authority
Maldon
Planning application reference
10/01070/FUL
Appeal reference
APP/X1545/A/12/2174982
Turbines
7
Address (REPD)
Turncole Farm, The Marshes, Southminster, Essex
Council area (by location)
Maldon
Time to decision
137 weeks
REPD reference
4067

Who decides

ApplicationsMaldonUK
Decided applications (solar, wind, battery)2010,236
Refused11 (55%)19%
Solar refused7 of 1312%
Onshore wind refused2 of 345%
Battery storage refused2 of 416%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Middlewick wind farmwind farm20.7operational2.1
Marshes Farmsolar farm25.5approved, not built2.3
Dengiesolar farm19approved, not built2.9
Wick Farm (Burnham on Crouch)solar farm5operational3.2
Bradwell Wind Farm (Repower)wind farm20operational7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6515, 0.8678).