Solar, wind and battery projects near Burnham-on-Crouch (CM0)
10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CM0 (Maldon): 2 are waiting for a planning decision, 4 approved but not yet running, 4 operational. The largest live scheme is Bolt Hall Farm, Lark Hill Road Solar Photovoltaic Farm. (50 MW solar farm, application submitted on 23 August 2023, no decision recorded; REPD status may be out of date), 8.6 km away. Offshore, 5 wind farms are recorded within 40 km; the nearest is Gunfleet Sands - (Demo) Extension (12 MW, operational), 25.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CM0
Projects of 1 MW and more (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Turncole Wind Farmwind farm | wind farm | 17.5 | operationalupdated Dec 2016 | Jun 2011 | granted Feb 2014 | Dec 2016 | Maldon | 2.7 |
| Marshes Farmsolar farm | solar farm | 25.5 | approved, not builtupdated Nov 2025 | Dec 2024 | granted Sep 2025 | Nov 2025 | Maldon | 2.8 |
| Dengiesolar farm | solar farm | 19 | approved, not builtupdated May 2024 | Dec 2023 | granted May 2024 | May 2024 | Maldon | 3.4 |
| Dengiebattery storage | battery storage | 5 | approved, not builtupdated May 2024 | Dec 2023 | granted May 2024 | May 2024 | Maldon | 3.4 |
| Wick Farm (Burnham on Crouch)solar farm | solar farm | 5 | operationalupdated Aug 2017 | Sep 2014 | granted Jan 2015 | Aug 2017 | Maldon | 3.9 |
| Middlewick wind farmwind farm | wind farm | 20.7 | operationalupdated Jan 2015 | Jan 2010 | granted May 2011 | Jan 2015 | Maldon | 4.1 |
| Bradwell Wind Farm (Repower)wind farm | wind farm | 20 | operationalupdated Jan 2014 | Mar 2006 | granted Jul 2006 | Jan 2014 | Maldon | 5.4 |
| Bolt Hall Farm, Lark Hill Road Solar Photovoltaic Farm.solar farm | solar farm | 50 | application submitted may be out of dateupdated Feb 2026 | Aug 2023 | — | Feb 2026 | Rochford | 8.6 |
Smaller schemes under 1 MW, mostly rooftop solar (2)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Dengie Crops Limited, Hall Roadwind turbine | wind turbine | — | application submittedupdated Jan 2026 | Oct 2025 | — | Jan 2026 | Maldon | 2.4 |
| Marshes Farmbattery storage | battery storage | — | approved, not builtupdated Nov 2025 | Dec 2024 | granted Sep 2025 | Nov 2025 | Maldon | 2.8 |
Distance from the average position of the CM0 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 1 | 2 | 1 | 0 | 94.5 |
| Wind farm | 3 | 0 | 0 | 3 | 0 | 0 |
| Wind turbine | 1 | 1 | 0 | 0 | 0 | 0 |
| Battery storage | 2 | 0 | 2 | 0 | 0 | 5 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Gunfleet Sands - (Demo) Extension | 12 | operationalupdated Nov 2017 | 25.2 |
| Gunfleet Sands Offshore Wind Scheme | 108 | operationalupdated May 2018 | 27.6 |
| Kentish Flats | 90 | operationalupdated Oct 2017 | 28.7 |
| Kentish Flats 2 | 49.5 | operationalupdated Jun 2016 | 29.1 |
| Gunfleet Sands II | 64.8 | operationalupdated Nov 2017 | 29.4 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Maldon decides solar, wind and battery applications
| Applications | Maldon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 20 | 10,236 |
| Refused | 11 (55%) | 19% |
| Solar refused | 7 of 13 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 2 of 4 | 16% |
| Median time from submission to decision | 19.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 4 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CM0, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.