Energy Projects Near You

Solar, wind and battery projects near Burnham-on-Crouch (CM0)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CM0 (Maldon): 2 are waiting for a planning decision, 4 approved but not yet running, 4 operational. The largest live scheme is Bolt Hall Farm, Lark Hill Road Solar Photovoltaic Farm. (50 MW solar farm, application submitted on 23 August 2023, no decision recorded; REPD status may be out of date), 8.6 km away. Offshore, 5 wind farms are recorded within 40 km; the nearest is Gunfleet Sands - (Demo) Extension (12 MW, operational), 25.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
2awaiting a decision
4approved, not running
4operational

Projects within 10 km of CM0

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Turncole Wind Farmwind farmwind farm17.5operationalupdated Dec 2016Jun 2011granted Feb 2014Dec 2016Maldon2.7
Marshes Farmsolar farmsolar farm25.5approved, not builtupdated Nov 2025Dec 2024granted Sep 2025Nov 2025Maldon2.8
Dengiesolar farmsolar farm19approved, not builtupdated May 2024Dec 2023granted May 2024May 2024Maldon3.4
Dengiebattery storagebattery storage5approved, not builtupdated May 2024Dec 2023granted May 2024May 2024Maldon3.4
Wick Farm (Burnham on Crouch)solar farmsolar farm5operationalupdated Aug 2017Sep 2014granted Jan 2015Aug 2017Maldon3.9
Middlewick wind farmwind farmwind farm20.7operationalupdated Jan 2015Jan 2010granted May 2011Jan 2015Maldon4.1
Bradwell Wind Farm (Repower)wind farmwind farm20operationalupdated Jan 2014Mar 2006granted Jul 2006Jan 2014Maldon5.4
Bolt Hall Farm, Lark Hill Road Solar Photovoltaic Farm.solar farmsolar farm50application submitted may be out of dateupdated Feb 2026Aug 2023—Feb 2026Rochford8.6
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dengie Crops Limited, Hall Roadwind turbinewind turbine—application submittedupdated Jan 2026Oct 2025—Jan 2026Maldon2.4
Marshes Farmbattery storagebattery storage—approved, not builtupdated Nov 2025Dec 2024granted Sep 2025Nov 2025Maldon2.8

Distance from the average position of the CM0 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4121094.5
Wind farm300300
Wind turbine110000
Battery storage202005

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Gunfleet Sands - (Demo) Extension12operationalupdated Nov 201725.2
Gunfleet Sands Offshore Wind Scheme108operationalupdated May 201827.6
Kentish Flats90operationalupdated Oct 201728.7
Kentish Flats 249.5operationalupdated Jun 201629.1
Gunfleet Sands II64.8operationalupdated Nov 201729.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Maldon decides solar, wind and battery applications

ApplicationsMaldonUK
Decided applications (solar, wind, battery)2010,236
Refused11 (55%)19%
Solar refused7 of 1312%
Onshore wind refused2 of 345%
Battery storage refused2 of 416%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

All projects in Maldon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CM0, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.