Gunfleet Sands is one of the operational offshore wind farms closest to shore: in a straight line from its point in the REPD, it is 7 km to the nearest postcode in Tendring, 8.5 km to the CO15 (Clacton-on-Sea) postcode district, and 12.1 km to CO16 and CO13 alike. It has 30 turbines of 3.6 MW each, 108 MW in total; the operator is Orsted (formerly Dong Energy).
Consent in 2004, construction in 2009
The application was submitted on 1 March 2002, and exactly two years later, on 1 March 2004, the minister granted consent under Section 36; the authority is recorded in the database as DECC. The wait took 104 weeks. Another five years passed before construction started: work began on 1 April 2009, and already on 24 July 2009 the wind farm was feeding power into the grid.
What's nearby
Closest of all are Gunfleet Sands II at 64.8 MW and the demonstration extension at 12 MW, 2 km and 3.6 km away, both operational. Further out is London Array Phase 1 at 630 MW, while Five Estuaries at 1,080 MW is approved, not built. The Gunfleet Sands record was last updated on 1 May 2018, and the stages shown come from the July 2026 extract.