Energy Projects Near You

Solar, wind and battery projects near Manningtree (CO11)

18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CO11 (Tendring): 2 are waiting for a planning decision, 9 approved but not yet running, 4 operational. The largest live scheme is Ardleigh Road, Little Bromley (50 MW battery storage, approved on 28 September 2022, not yet built; REPD status may be out of date), 5.0 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Gunfleet Sands Offshore Wind Scheme (108 MW, operational), 25.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18projects within 10 km
2awaiting a decision
9approved, not running
4operational

Projects within 10 km of CO11

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land North of Horsley Cross Solar Farm & Battery Energy Storagesolar farmsolar farm34application submittedupdated Sep 2025Jul 2025—Sep 2025Tendring2.9
Barn Farmsolar farmsolar farm4.2operationalupdated Aug 2015Jul 2014granted Oct 2014Aug 2015Tendring4.1
Wix Lodgesolar farmsolar farm18.7operationalupdated Apr 2014Aug 2013granted Nov 2013Apr 2014Tendring4.6
Ardleigh Road, Little Bromleybattery storagebattery storage50approved, not built may be out of dateupdated Nov 2022Dec 2021granted Sep 2022Nov 2022Tendring5.0
Burnt Ash Farmsolar farmsolar farm13.5refused on appealupdated Oct 2015Dec 2013refused Aug 2014Oct 2015Tendring5.3
Green Farmsolar farmsolar farm5operationalupdated Feb 2016Feb 2015granted May 2015Feb 2016Tendring6.2
Primrose Hall Solar Farmsolar farmsolar farm20approved, not built may be out of dateupdated Mar 2023Oct 2020granted Mar 2021Mar 2023Tendring6.5
Chancery Farm (Ardleigh)solar farmsolar farm11.9operationalupdated Mar 2017Apr 2014granted Dec 2015Mar 2017Tendring6.7
Coxhall Road, Tattingstonebattery storagebattery storage5approved, not built may be out of dateupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Babergh7.0
Valley Farmsolar farmsolar farm16refused on appealupdated Jul 2014Feb 2013refused Jun 2013Jul 2014Babergh7.1
Martells Quarry, Slough Lanesolar farmsolar farm1approved, not builtupdated Jan 2026Sep 2025granted Dec 2025Jan 2026Tendring7.2
Pannington Hallwind turbinewind turbine3refusedupdated Jan 2015Dec 2013refused Dec 2014Jan 2015Babergh9.7
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land North of Horsley Cross Solar Farm & Battery Energy Storagebattery storagebattery storage—application submittedupdated Sep 2025Jul 2025—Sep 2025Tendring2.9
Treestacks Farm, Oakley Roadrooftop solarrooftop solar—approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025Tendring7.5
Manheim Colchester Auctions, Colchester Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Tendring8.0
Penguin Random House Distribution, Colchester Roadrooftop solarrooftop solar0.9approved, not builtupdated Jan 2024Dec 2023granted Jan 2024Jan 2024Tendring8.2
Waste Transfer Station, Ardleighbattery storagebattery storage0.2approved, not builtupdated Sep 2025May 2025granted Sep 2025Sep 2025Tendring8.2
Park Farm House, Vicarage Lanebattery storagebattery storage0.2approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Babergh9.9

Distance from the average position of the CO11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm9124255
Rooftop solar303001.1
Wind turbine100010
Battery storage5140055.4

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Gunfleet Sands Offshore Wind Scheme108operationalupdated May 201825.4
Gunfleet Sands II64.8operationalupdated Nov 201726.6
Gunfleet Sands - (Demo) Extension12operationalupdated Nov 201727.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Tendring decides solar, wind and battery applications

ApplicationsTendringUK
Decided applications (solar, wind, battery)2610,236
Refused10 (38%)19%
Solar refused5 of 1912%
Onshore wind refused4 of 445%
Battery storage refused1 of 316%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Tendring

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CO11, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.