Valley Farm (16 MW solar farm)

Valley Farm is a 16 MW solar farm project in Babergh, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 2 June 2014; the record was last updated on 3 July 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWsolar farm
refused on appealstatus in REPD
3 July 2014record last updated
Baberghcouncil area

Planning timeline

DateStage
18 February 2013Application submitted
12 June 2013Refused by the planning authority
2 June 2014Appeal refused

Project details

Technology
solar farm
Capacity
16 MW
Status (REPD)
refused on appeal
Record last updated
3 July 2014
Operator or applicant
Hive Energy
Planning authority
Babergh
Planning application reference
B/12/01279
Site area
38.4 ha
Address (REPD)
Cox Hall Road, Tattingstone
Council area (by location)
Babergh
Time to decision
16 weeks
REPD reference
1778

Who decides

ApplicationsBaberghUK
Decided applications (solar, wind, battery)1110,236
Refused3 (27%)19%
Solar refused2 of 512%
Onshore wind refused1 of 145%
Battery storage refused0 of 516%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Coxhall Road, Tattingstonebattery storage5approved, not built1.1
Burnt Ash Farmsolar farm13.5refused on appeal8.7
Bullen Lanebattery storage100under construction9.0
Bramford Substationbattery storage57operational9.2
Land North of Horsley Cross Solar Farm & Battery Energy Storagesolar farm34application submitted9.5
Wix Lodgesolar farm18.7operational9.5
Primrose Hall Solar Farmsolar farm20approved, not built9.6
Bullen Lane, Bramfordbattery storage400approved, not built9.7
Green Farmsolar farm5operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9986, 1.1257).