Burnt Ash Farm (13.5 MW solar farm)

Burnt Ash Farm is a 13.5 MW solar farm project in Tendring, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 8 September 2015; the record was last updated on 26 October 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.5 MWsolar farm
refused on appealstatus in REPD
26 October 2015record last updated
Tendringcouncil area

Planning timeline

DateStage
17 December 2013Application submitted
1 August 2014Refused by the planning authority
29 September 2014Appeal lodged
8 September 2015Appeal refused

Project details

Technology
solar farm
Capacity
13.5 MW
Status (REPD)
refused on appeal
Record last updated
26 October 2015
Operator or applicant
Kinetica Solar
Planning authority
Tendring
Planning application reference
13/01340/FUL
Appeal reference
14/00055/REFUSE
Site area
25.7 ha
Address (REPD)
Burnt Ash Farm Spinnels Lane Wix Manningtree Essex
Council area (by location)
Tendring
Time to decision
32 weeks
REPD reference
1977

Who decides

ApplicationsTendringUK
Decided applications (solar, wind, battery)2610,236
Refused10 (38%)19%
Solar refused5 of 1912%
Onshore wind refused4 of 445%
Battery storage refused1 of 316%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Green Farmsolar farm5operational1.1
Primrose Hall Solar Farmsolar farm20approved, not built1.2
Wix Lodgesolar farm18.7operational1.8
Land North of Horsley Cross Solar Farm & Battery Energy Storagesolar farm34application submitted4.2
Solar Farm at Thorpe Park Solar Farm Land South of Thorpe-Le-Sokensolar farm40approved, not built8.4
Valley Farmsolar farm16refused on appeal8.7
Ardleigh Road, Little Bromleybattery storage50approved, not built9.0
Coxhall Road, Tattingstonebattery storage5approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9213, 1.1469).