Energy Projects Near You

Coxhall Road, Tattingstone (5 MW battery storage)

Coxhall Road, Tattingstone is a 5 MW battery storage project in Babergh, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 January 2023, not yet built; the record was last updated on 24 January 2023. REPD also records that the planning permission expired on 17 January 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWbattery storage
approved, not builtmay be out of datestatus in REPD
24 January 2023record last updated
Baberghcouncil area

REPD also records that the planning permission expired on 17 January 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
15 November 2022Application submitted
17 January 2023Planning permission granted
17 January 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
24 January 2023
Operator or applicant
AMP Energy Services Limited
Planning authority
Babergh
Planning application reference
DC/22/05668
Address (REPD)
South Of Coxhall Road Tattingstone
Council area (by location)
Babergh
Time to decision
9 weeks
Name in REPD
Coxhall Road, Tattingstone - Battery Storage
REPD reference
12693

Earlier applications for this site

ApplicationMWSubmittedOutcome
Coxhall Road, Tattingstone DC/22/0386254 August 2022withdrawn 26 September 2022

Who decides

ApplicationsBaberghUK
Decided applications (solar, wind, battery)1110,236
Refused3 (27%)19%
Solar refused2 of 512%
Onshore wind refused1 of 145%
Battery storage refused0 of 516%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Valley Farmsolar farm16refused on appeal1.1
Bullen Lanebattery storage100under construction8.5
Bramford Substationbattery storage57operational8.5
Bullen Lane, Bramfordbattery storage400approved, not built9.0
Burnt Ash Farmsolar farm13.5refused on appeal9.3
Tye Lane Solar Farmsolar farm49.9under construction9.4
Church Farm, The Channel - Bramford Solar Farm and Battery Storagesolar farm49.9approved, not built9.5
Greybarn Solar Energy Farmsolar farm41.5application submitted9.6
Land North of Horsley Cross Solar Farm & Battery Energy Storagesolar farm34application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0015, 1.1108).