Bullen Lane, Bramford (400 MW battery storage)

Bullen Lane, Bramford is a 400 MW battery storage project in Mid Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 March 2025, not yet built; the record was last updated on 4 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus in REPD
4 April 2025record last updated
Mid Suffolkcouncil area

Planning timeline

DateStage
21 November 2024Application submitted
27 March 2025Planning permission granted
27 March 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
4 April 2025
Operator or applicant
Clearstone Energy Limited
Planning authority
Mid Suffolk
Planning application reference
DC/24/05090
Address (REPD)
Adj To Bullen Lane, Bramford, Ipswich
Council area (by location)
Mid Suffolk
Time to decision
18 weeks
Name in REPD
Bullen Lane, Bramford - Battery Energy Storage
REPD reference
17754

Who decides

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bramford Substationbattery storage57operational0.6
Tye Lane Solar Farmsolar farm49.9under construction0.9
Church Farm, The Channel - Bramford Solar Farm and Battery Storagesolar farm49.9approved, not built1.8
Bullen Lanebattery storage100under construction1.9
Greybarn Solar Energy Farmsolar farm41.5application submitted2.5
Masons Landfill, Bramford Road, Great Blakenham Solar Farmsolar farm6.1approved, not built3.9
Land at Hill Farmsolar farm10application withdrawn4.5
Hill Farm (Baylham)solar farm10application withdrawn4.5
Coxhall Road, Tattingstonebattery storage5approved, not built9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0779, 1.0674).