Energy Projects Near You

Bullen Lane (100 MW battery storage)

Bullen Lane is a 100 MW battery storage project in Mid Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 July 2023; the record was last updated on 5 December 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
under constructionstatus in REPD
5 December 2023record last updated
Mid Suffolkcouncil area

Planning timeline

DateStage
5 October 2021Application submitted
5 January 2022Planning permission granted
1 July 2023Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
under construction
Record last updated
5 December 2023
Operator or applicant
Cambridge Power Limited / Pivot Power
Planning authority
Mid Suffolk
Planning application reference
DC/21/05468
Address (REPD)
S/O Bullen Lane
Council area (by location)
Mid Suffolk
Time to decision
13 weeks
Name in REPD
Bullen Lane - Battery Storage
REPD reference
10311

Who decides

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tye Lane Solar Farmsolar farm49.9under construction1.4
Bullen Lane, Bramfordbattery storage400approved, not built1.9
Bramford Substationbattery storage57operational2.1
Masons Landfill, Bramford Road, Great Blakenham Solar Farmsolar farm6.1approved, not built3.5
Church Farm, The Channel - Bramford Solar Farm and Battery Storagesolar farm49.9approved, not built3.6
Greybarn Solar Energy Farmsolar farm41.5application submitted4.3
Land at Hill Farmsolar farm10application withdrawn4.6
Hill Farm (Baylham)solar farm10application withdrawn4.6
Coxhall Road, Tattingstonebattery storage5approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0774, 1.0945).