Solar, wind and battery projects near Ipswich (IP3)
35 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IP3 (Ipswich): 1 is waiting for a planning decision, 25 approved but not yet running, 5 operational. The largest live scheme is Bullen Lane, Bramford (400 MW battery storage, approved on 27 March 2025, not yet built), 9.2 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Gunfleet Sands Offshore Wind Scheme (108 MW, operational), 34.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of IP3
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Pannington Hallwind turbine | wind turbine | 3 | refusedupdated Jan 2015 | Dec 2013 | refused Dec 2014 | Jan 2015 | Babergh | 5.2 |
| Valley Farmsolar farm | solar farm | 16 | refused on appealupdated Jul 2014 | Feb 2013 | refused Jun 2013 | Jul 2014 | Babergh | 6.4 |
| Bucklesham Solar Farmsolar farm | solar farm | 25 | approved, not builtupdated Feb 2026 | Jan 2023 | granted Nov 2023 | Feb 2026 | East Suffolk | 6.6 |
| Foxburrow Farmsolar farm | solar farm | 8 | operationalupdated Jan 2014 | Aug 2013 | granted Nov 2013 | Jan 2014 | East Suffolk | 6.6 |
| Coxhall Road, Tattingstonebattery storage | battery storage | 5 | approved, not built may be out of dateupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Babergh | 6.9 |
| Suffolk Yacht Harbour, Levingtonsolar farm | solar farm | 1.2 | approved, not builtupdated Jun 2026 | Nov 2025 | granted Jan 2026 | Jun 2026 | East Suffolk | 7.5 |
| Bullen Lanebattery storage | battery storage | 100 | under constructionupdated Dec 2023 | Oct 2021 | granted Jan 2022 | Dec 2023 | Mid Suffolk | 7.5 |
| Stratton Hall Solar Parksolar farm | solar farm | 11.6 | operationalupdated Aug 2014 | Oct 2012 | granted Mar 2013 | Aug 2014 | East Suffolk | 7.7 |
| Tye Lane Solar Farmsolar farm | solar farm | 49.9 | under constructionupdated Mar 2026 | Sep 2021 | granted Dec 2023 | Mar 2026 | Mid Suffolk | 8.9 |
| Bramford Substationbattery storage | battery storage | 57 | operationalupdated Mar 2026 | Jun 2019 | granted Nov 2021 | Mar 2026 | Mid Suffolk | 9.1 |
| Bullen Lane, Bramfordbattery storage | battery storage | 400 | approved, not builtupdated Apr 2025 | Nov 2024 | granted Mar 2025 | Apr 2025 | Mid Suffolk | 9.2 |
| Masons Landfill, Bramford Road, Great Blakenham Solar Farmsolar farm | solar farm | 6.1 | approved, not builtupdated Apr 2024 | Sep 2022 | granted Mar 2024 | Apr 2024 | Mid Suffolk | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Raeburn Road South and Gainsborough Lane - Micro Energy Storage Systembattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | May 2025 | granted Aug 2025 | Nov 2025 | Ipswich | 1.5 |
| Clarkson Port Services, Cliff Quay Solar Panlesrooftop solar | rooftop solar | 0.9 | approved, not built may be out of dateupdated Oct 2022 | Aug 2022 | granted Sep 2022 | Oct 2022 | Ipswich | 1.9 |
| University Of Suffolk Campus Northbattery storage | battery storage | — | operationalupdated Mar 2020 | Mar 2020 | granted Sep 2021 | Mar 2020 | Ipswich | 2.1 |
| Bluestem Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Ipswich | 2.1 |
| Rope Walkrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2024 | Jun 2024 | granted Aug 2024 | Aug 2024 | Ipswich | 2.2 |
| Marguerite Jeffries Centre - Micro Energy Storage Unitbattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2024 | Jul 2024 | granted Oct 2024 | Nov 2024 | Ipswich | 2.4 |
| David Lloyd Leisurerooftop solar | rooftop solar | — | approved, not builtupdated Nov 2025 | Aug 2025 | granted Sep 2025 | Nov 2025 | Ipswich | 2.4 |
| Crown Car Park - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Ipswich | 3.1 |
| Outside Crown House, Crown Street - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Aug 2025 | May 2025 | granted Jul 2025 | Aug 2025 | Ipswich | 3.1 |
| Amenity Land Opp To Crown Court, Chancery Road - Micro Battery Storagebattery storage | battery storage | 0.2 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | Ipswich | 3.4 |
| Birkfield Drive - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Ipswich | 3.8 |
| Park Farm House, Vicarage Lanebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 | Babergh | 3.9 |
| Gatacre Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Ipswich | 4.2 |
| Ipswich High School, Main Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jul 2025 | Sep 2024 | granted Dec 2024 | Jul 2025 | Babergh | 4.3 |
| Sainsburys Supermarkets, Hadleigh Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2025 | Aug 2025 | granted Sep 2025 | Oct 2025 | Ipswich | 4.3 |
| Westbourne Branch Library, Sherrington Road - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Ipswich | 4.4 |
| Anson Road, Martlesham -Solar Panelsrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Jan 2025 | Feb 2025 | East Suffolk | 6.8 |
| White House Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Aug 2023 | granted Sep 2023 | Sep 2023 | Ipswich | 6.9 |
| Beacon House, White House Roadbattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Feb 2025 | Mar 2025 | Ipswich | 6.9 |
| Suffolk Yacht Harbour, Levingtonbattery storage | battery storage | — | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | East Suffolk | 7.5 |
| Tye Lane Solar Farmbattery storage | battery storage | — | operationalupdated Mar 2026 | Sep 2021 | granted Dec 2023 | Mar 2026 | Mid Suffolk | 8.9 |
| Bliney Road, Grove Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application withdrawnupdated Aug 2024 | Jul 2024 | — | Aug 2024 | East Suffolk | 9.8 |
| Bliney Road, Grove Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application withdrawnupdated Aug 2024 | Jul 2024 | — | Aug 2024 | East Suffolk | 9.8 |
Distance from the average position of the IP3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 4 | 2 | 1 | 82.2 |
| Rooftop solar | 8 | 0 | 8 | 0 | 0 | 2.6 |
| Wind turbine | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 19 | 1 | 13 | 3 | 0 | 507 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Gunfleet Sands Offshore Wind Scheme | 108 | operationalupdated May 2018 | 34.6 |
| Gunfleet Sands II | 64.8 | operationalupdated Nov 2017 | 35.2 |
| Gunfleet Sands - (Demo) Extension | 12 | operationalupdated Nov 2017 | 37.6 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Ipswich decides solar, wind and battery applications
| Applications | Ipswich | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 16 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Battery storage refused | 0 of 10 | 16% |
| Median time from submission to decision | 7.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IP3, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.