Energy Projects Near You

Masons Landfill, Bramford Road, Great Blakenham Solar Farm (6.1 MW)

Masons Landfill, Bramford Road, Great Blakenham Solar Farm is a 6.1 MW solar farm project in Mid Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 March 2024, not yet built; the record was last updated on 2 April 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.1 MWsolar farm
approved, not builtstatus in REPD
2 April 2024record last updated
Mid Suffolkcouncil area

Planning timeline

DateStage
2 September 2022Application submitted
19 March 2024Planning permission granted
19 March 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
6.1 MW
Status (REPD)
approved, not built
Record last updated
2 April 2024
Operator or applicant
Valencia Waster Management Limited
Planning authority
Mid Suffolk
Planning application reference
SCC/0083/22MS
Site area
6.8 ha
Address (REPD)
Masons Landfill, Bramford Road, Great Blakenham
Council area (by location)
Mid Suffolk
Time to decision
81 weeks
Name in REPD
Masons Landfill, Bramford Road, Great Blakenham - Solar Farm
REPD reference
11683

Who decides

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Hill Farmsolar farm10application withdrawn1.4
Hill Farm (Baylham)solar farm10application withdrawn1.4
Tye Lane Solar Farmsolar farm49.9under construction3.0
Bullen Lanebattery storage100under construction3.5
Bullen Lane, Bramfordbattery storage400approved, not built3.9
Bramford Substationbattery storage57operational4.4
Church Farm, The Channel - Bramford Solar Farm and Battery Storagesolar farm49.9approved, not built5.1
Greybarn Solar Energy Farmsolar farm41.5application submitted5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1086, 1.0935).