Energy Projects Near You

Land at Hill Farm (10 MW solar farm)

Land at Hill Farm is a 10 MW solar farm project in Mid Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 23 May 2013; the record was last updated on 13 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
application withdrawnstatus in REPD
13 June 2013record last updated
Mid Suffolkcouncil area

Planning timeline

DateStage
19 February 2013Application submitted
23 May 2013Application withdrawn

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
application withdrawn
Record last updated
13 June 2013
Operator or applicant
Hive Energy
Planning authority
Mid Suffolk
Planning application reference
3319/12
Site area
20.4 ha
Address (REPD)
Baylham, Suffolk
Council area (by location)
Mid Suffolk
REPD reference
1182

Who decides

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill Farm (Baylham)solar farm10application withdrawn<0.1
Masons Landfill, Bramford Road, Great Blakenham Solar Farmsolar farm6.1approved, not built1.4
Tye Lane Solar Farmsolar farm49.9under construction3.7
Bullen Lane, Bramfordbattery storage400approved, not built4.5
Bullen Lanebattery storage100under construction4.6
Bramford Substationbattery storage57operational5.0
Church Farm, The Channel - Bramford Solar Farm and Battery Storagesolar farm49.9approved, not built5.2
Greybarn Solar Energy Farmsolar farm41.5application submitted5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1174, 1.0782).