Bramford Substation (57 MW battery storage)

Bramford Substation is a 57 MW battery storage project in Mid Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2025; the record was last updated on 6 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWbattery storage
operationalstatus in REPD
6 March 2026record last updated
Mid Suffolkcouncil area

Planning timeline

DateStage
25 June 2019Application submitted
1 November 2021Planning permission granted
1 June 2023Construction started
1 April 2025Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
57 MW
Status (REPD)
operational
Record last updated
6 March 2026
Operator or applicant
Pivot Power / EDF Renewables
Planning authority
Mid Suffolk
Planning application reference
DC/19/03008
Address (REPD)
Land Adjacent To, Bullen Lane, Bramford, Ipswich, Suffolk
Council area (by location)
Mid Suffolk
Time to decision
123 weeks
REPD reference
7479

Who decides

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bullen Lane, Bramfordbattery storage400approved, not built0.6
Tye Lane Solar Farmsolar farm49.9under construction1.5
Church Farm, The Channel - Bramford Solar Farm and Battery Storagesolar farm49.9approved, not built1.6
Bullen Lanebattery storage100under construction2.1
Greybarn Solar Energy Farmsolar farm41.5application submitted2.3
Masons Landfill, Bramford Road, Great Blakenham Solar Farmsolar farm6.1approved, not built4.4
Land at Hill Farmsolar farm10application withdrawn5.0
Hill Farm (Baylham)solar farm10application withdrawn5.1
Coxhall Road, Tattingstonebattery storage5approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0729, 1.065).