Energy Projects Near You

Solar, wind and battery projects near Ipswich (IP7)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IP7 (Babergh): 2 are waiting for a planning decision, 4 approved but not yet running, 3 operational. The largest live scheme is Bullen Lane, Bramford (400 MW battery storage, approved on 27 March 2025, not yet built), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
2awaiting a decision
4approved, not running
3operational

Projects within 10 km of IP7

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Babergh Home Solar Schemerooftop solarrooftop solar2.8operationalupdated Aug 2016——Aug 2016Babergh2.2
Greybarn Solar Energy Farmbattery storagebattery storage55application submitted may be out of dateupdated Oct 2024Mar 2022—Oct 2024Mid Suffolk6.0
Greybarn Solar Energy Farmsolar farmsolar farm41.5application submitted may be out of dateupdated Oct 2024Mar 2022—Oct 2024Mid Suffolk6.0
Church Farm, The Channel - Bramford Solar Farm and Battery Storagesolar farmsolar farm49.9approved, not builtupdated Oct 2024May 2023granted Sep 2023Oct 2024Mid Suffolk6.8
Bramford Substationbattery storagebattery storage57operationalupdated Mar 2026Jun 2019granted Nov 2021Mar 2026Mid Suffolk8.3
Bullen Lane, Bramfordbattery storagebattery storage400approved, not builtupdated Apr 2025Nov 2024granted Mar 2025Apr 2025Mid Suffolk8.5
Tye Lane Solar Farmsolar farmsolar farm49.9under constructionupdated Mar 2026Sep 2021granted Dec 2023Mar 2026Mid Suffolk9.3
Rogers Farmsolar farmsolar farm15refused on appealupdated Jun 2016Sep 2013refused Feb 2014Jun 2016Babergh9.5
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Beaumont Park, Red Hill Road - Micro Energy Storagebattery storagebattery storage0.2application withdrawnupdated Apr 2025Feb 2025—Apr 2025Babergh2.0
Church Farm, The Channel - Bramford Solar Farm and Battery Storagebattery storagebattery storage—approved, not builtupdated Oct 2024May 2023granted Sep 2023Oct 2024Mid Suffolk6.8
Tye Lane Solar Farmbattery storagebattery storage—operationalupdated Mar 2026Sep 2021granted Dec 2023Mar 2026Mid Suffolk9.3

Distance from the average position of the IP7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm41201141
Rooftop solar100100
Battery storage61220455

MW in pipeline: pending, approved and under-construction capacity.

How Babergh decides solar, wind and battery applications

ApplicationsBaberghUK
Decided applications (solar, wind, battery)1110,236
Refused3 (27%)19%
Solar refused2 of 512%
Onshore wind refused1 of 145%
Battery storage refused0 of 516%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Babergh

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IP7, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.