Solar Farm at Thorpe Park Solar Farm Land South of Thorpe-Le-Soken (40 MW)

Solar Farm at Thorpe Park Solar Farm Land South of Thorpe-Le-Soken is a 40 MW solar farm project in Tendring, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 February 2023, not yet built; the record was last updated on 22 February 2023. REPD records the planning permission as expiring on 17 February 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtmay be out of datestatus in REPD
22 February 2023record last updated
Tendringcouncil area

REPD records the planning permission as expiring on 17 February 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
19 December 2022Application submitted
17 February 2023Planning permission granted
17 February 2026Permission expired

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
22 February 2023
Operator or applicant
Low Carbon UK Solar Investment Co Limited
Planning authority
Tendring
Planning application reference
22/02117/FUL
Site area
54.9 ha
Address (REPD)
Thorpe Park Solar Farm Land South of Thorpe-Le-Soken, Clacton on Sea
Council area (by location)
Tendring
Time to decision
9 weeks
Contracts for Difference
AR5
Name in REPD
Thorpe Park Solar Farm, Thorpe Le Soken - Solar Farm
REPD reference
13028

Earlier applications for this site

ApplicationMWSubmittedOutcome
Thorpe Park Solar Farm 21/01860/FUL3027 October 2021refused 1 August 2022

Who decides

ApplicationsTendringUK
Decided applications (solar, wind, battery)2610,236
Refused10 (38%)19%
Solar refused5 of 1912%
Onshore wind refused4 of 445%
Battery storage refused1 of 316%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Halstead Road Eco Hub Solar Farm & Battery Storagesolar farm26refused3.7
Sladburys Farmsolar farm12application withdrawn3.8
Holland Roadsolar farm12refused3.8
Hartley Wood Farm Solar Farmsolar farm22.5approved, not built5.3
Earl's Hallwind farm10.3operational7.0
Green Farmsolar farm5operational7.3
Primrose Hall Solar Farmsolar farm20approved, not built7.4
Chisbon Solar Farm (Frowick Lane)solar farm13operational7.6
Wix Lodgesolar farm18.7operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8503, 1.1883).