Solar Farm at Thorpe Park Solar Farm Land South of Thorpe-Le-Soken (40 MW)
Solar Farm at Thorpe Park Solar Farm Land South of Thorpe-Le-Soken is a 40 MW solar farm project in Tendring, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 February 2023, not yet built; the record was last updated on 22 February 2023. REPD records the planning permission as expiring on 17 February 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.
approved, not builtmay be out of datestatus in REPD
22 February 2023record last updated
Tendringcouncil area
application
approved
under construction
operational
REPD records the planning permission as expiring on 17 February 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started.
Planning timeline
Date
Stage
19 December 2022
Application submitted
17 February 2023
Planning permission granted
17 February 2026
Permission expired
Project details
Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
22 February 2023
Operator or applicant
Low Carbon UK Solar Investment Co Limited
Planning authority
Tendring
Planning application reference
22/02117/FUL
Site area
54.9 ha
Address (REPD)
Thorpe Park Solar Farm Land South of Thorpe-Le-Soken, Clacton on Sea
Council area (by location)
Tendring
Time to decision
9 weeks
Contracts for Difference
AR5
Name in REPD
Thorpe Park Solar Farm, Thorpe Le Soken - Solar Farm
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8503, 1.1883).