Energy Projects Near You

Holland Road (12 MW solar farm)

Holland Road is a 12 MW solar farm project in Tendring, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 February 2014; the record was last updated on 1 April 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
refusedstatus in REPD
1 April 2014record last updated
Tendringcouncil area

Planning timeline

DateStage
13 November 2013Application submitted
12 February 2014Refused by the planning authority

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
refused
Record last updated
1 April 2014
Operator or applicant
Push Energy
Planning authority
Tendring
Planning application reference
13/01292/FUL
Site area
25.9 ha
Address (REPD)
Land adjacent to Electricity Substation Holland Road Little Clacton Essex CO16 9QG
Council area (by location)
Tendring
Time to decision
13 weeks
REPD reference
1460

Who decides

ApplicationsTendringUK
Decided applications (solar, wind, battery)2610,236
Refused10 (38%)19%
Solar refused5 of 1912%
Onshore wind refused4 of 445%
Battery storage refused1 of 316%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sladburys Farmsolar farm12application withdrawn<0.1
Solar Farm at Thorpe Park Solar Farm Land South of Thorpe-Le-Sokensolar farm40approved, not built3.8
Halstead Road Eco Hub Solar Farm & Battery Storagesolar farm26refused4.8
Hartley Wood Farm Solar Farmsolar farm22.5approved, not built5.2
Earl's Hallwind farm10.3operational5.3
Clay Lane, St Osyth Solar Farmsolar farm20approved, not built6.6
Chisbon Solar Farm (Frowick Lane)solar farm13operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8165, 1.1877).