Energy Projects Near You

Solar, wind and battery projects near Frinton-on-Sea (CO13)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CO13 (Tendring): 4 approved but not yet running, 2 operational. The largest live scheme is Solar Farm at Thorpe Park Solar Farm Land South of Thorpe-Le-Soken (40 MW solar farm, approved on 17 February 2023, not yet built; REPD status may be out of date), 3.5 km away. Offshore, 4 wind farms are recorded within 40 km; the nearest is Gunfleet Sands Offshore Wind Scheme (108 MW, operational), 12.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
0awaiting a decision
4approved, not running
2operational

Projects within 10 km of CO13

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Halstead Road Eco Hub Solar Farm & Battery Storagesolar farmsolar farm26refusedupdated Oct 2021Jan 2022refused Nov 2022Oct 2021Tendring0.7
Halstead Road Eco Hub Solar Farm & Battery Storagebattery storagebattery storage3refusedupdated Oct 2021Jan 2022refused Nov 2022Oct 2021Tendring0.7
Solar Farm at Thorpe Park Solar Farm Land South of Thorpe-Le-Sokensolar farmsolar farm40approved, not built may be out of dateupdated Feb 2023Dec 2022granted Feb 2023Feb 2023Tendring3.5
Holland Roadsolar farmsolar farm12refusedupdated Apr 2014Nov 2013refused Feb 2014Apr 2014Tendring4.2
Sladburys Farmsolar farmsolar farm12application withdrawnupdated Nov 2013Aug 2013—Nov 2013Tendring4.2
Hartley Wood Farm Solar Farmsolar farmsolar farm22.5approved, not builtupdated Sep 2022Mar 2022granted Aug 2022Sep 2022Tendring8.2
Earl's Hallwind farmwind farm10.3operationalupdated Jan 2015Mar 2007granted Nov 2009Jan 2015Tendring9.2
Primrose Hall Solar Farmsolar farmsolar farm20approved, not built may be out of dateupdated Mar 2023Oct 2020granted Mar 2021Mar 2023Tendring9.9
Green Farmsolar farmsolar farm5operationalupdated Feb 2016Feb 2015granted May 2015Feb 2016Tendring9.9
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Treestacks Farm, Oakley Roadrooftop solarrooftop solar—approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025Tendring8.8

Distance from the average position of the CO13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7031282.5
Rooftop solar101000
Wind farm100100
Battery storage100010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Gunfleet Sands Offshore Wind Scheme108operationalupdated May 201812.1
Gunfleet Sands II64.8operationalupdated Nov 201712.5
Gunfleet Sands - (Demo) Extension12operationalupdated Nov 201715.5
London Array Phase 1630operationalupdated Nov 201830.1

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Tendring decides solar, wind and battery applications

ApplicationsTendringUK
Decided applications (solar, wind, battery)2610,236
Refused10 (38%)19%
Solar refused5 of 1912%
Onshore wind refused4 of 445%
Battery storage refused1 of 316%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Tendring

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CO13, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.