Green Farm (5 MW solar farm)

Green Farm is a 5 MW solar farm project in Tendring, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2015; the record was last updated on 16 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
16 February 2016record last updated
Tendringcouncil area

Planning timeline

DateStage
4 February 2015Application submitted
6 May 2015Planning permission granted
1 November 2015Construction started
1 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
16 February 2016
Operator or applicant
Hive Energy
Planning authority
Tendring
Planning application reference
15/00147/FUL
Site area
15.0 ha
Address (REPD)
Green Farm, Oakley Road, Wix
Council area (by location)
Tendring
Time to decision
13 weeks
REPD reference
5089

Earlier applications for this site

ApplicationMWSubmittedOutcome
Green Farm (Wix Manningtree) 13/01210/FUL78 November 2013refused 7 February 2014

Who decides

ApplicationsTendringUK
Decided applications (solar, wind, battery)2610,236
Refused10 (38%)19%
Solar refused5 of 1912%
Onshore wind refused4 of 445%
Battery storage refused1 of 316%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Primrose Hall Solar Farmsolar farm20approved, not built0.6
Burnt Ash Farmsolar farm13.5refused on appeal1.1
Wix Lodgesolar farm18.7operational2.0
Land North of Horsley Cross Solar Farm & Battery Energy Storagesolar farm34application submitted4.6
Solar Farm at Thorpe Park Solar Farm Land South of Thorpe-Le-Sokensolar farm40approved, not built7.3
Hartley Wood Farm Solar Farmsolar farm22.5approved, not built9.2
Ardleigh Road, Little Bromleybattery storage50approved, not built9.4
Halstead Road Eco Hub Solar Farm & Battery Storagesolar farm26refused9.6
Valley Farmsolar farm16refused on appeal9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9119, 1.1535).