Energy Projects Near You

Primrose Hall Solar Farm (20 MW)

Primrose Hall Solar Farm is a 20 MW solar farm project in Tendring, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 March 2021, not yet built; the record was last updated on 21 March 2023. REPD records the planning permission as expiring on 19 March 2024, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtmay be out of datestatus in REPD
21 March 2023record last updated
Tendringcouncil area

REPD records the planning permission as expiring on 19 March 2024, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
2 October 2020Application submitted
19 March 2021Planning permission granted
19 March 2024Permission expired

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
21 March 2023
Operator or applicant
Low Carbon Limited
Planning authority
Tendring
Planning application reference
20/01384/FUL
Site area
28.5 ha
Address (REPD)
S/O Primrose Hall
Council area (by location)
Tendring
Time to decision
24 weeks
Contracts for Difference
AR5
REPD reference
8020

Who decides

ApplicationsTendringUK
Decided applications (solar, wind, battery)2610,236
Refused10 (38%)19%
Solar refused5 of 1912%
Onshore wind refused4 of 445%
Battery storage refused1 of 316%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Green Farmsolar farm5operational0.6
Burnt Ash Farmsolar farm13.5refused on appeal1.2
Wix Lodgesolar farm18.7operational2.6
Land North of Horsley Cross Solar Farm & Battery Energy Storagesolar farm34application submitted5.1
Solar Farm at Thorpe Park Solar Farm Land South of Thorpe-Le-Sokensolar farm40approved, not built7.4
Halstead Road Eco Hub Solar Farm & Battery Storagesolar farm26refused9.6
Valley Farmsolar farm16refused on appeal9.6
Hartley Wood Farm Solar Farmsolar farm22.5approved, not built9.7
Ardleigh Road, Little Bromleybattery storage50approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9149, 1.1611).