Chancery Farm (Ardleigh) (11.9 MW solar farm)

Chancery Farm (Ardleigh) is an 11.9 MW solar farm project in Tendring, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2016; the record was last updated on 1 March 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.9 MWsolar farm
operationalstatus in REPD
1 March 2017record last updated
Tendringcouncil area

Planning timeline

DateStage
15 April 2014Application submitted
22 December 2015Planning permission granted
23 December 2015Construction started
29 March 2016Operational

Project details

Technology
solar farm
Capacity
11.9 MW
Status (REPD)
operational
Record last updated
1 March 2017
Operator or applicant
BlackRock
Planning authority
Tendring
Planning application reference
14/00408/FUL
Site area
16.9 ha
Address (REPD)
Chancery Farm, Park Road, Ardleigh, Colchester
Council area (by location)
Tendring
Time to decision
88 weeks
REPD reference
1946

Who decides

ApplicationsTendringUK
Decided applications (solar, wind, battery)2610,236
Refused10 (38%)19%
Solar refused5 of 1912%
Onshore wind refused4 of 445%
Battery storage refused1 of 316%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ardleigh Road, Little Bromleybattery storage50approved, not built1.7
Stephenson Road - Urban Reserve Flexible Energy Facilitybattery storage6approved, not built4.4
Bluegates Solar Parksolar farm10.5operational5.6
Boxted Airfieldsolar farm18.8operational5.7
Land North of Horsley Cross Solar Farm & Battery Energy Storagesolar farm34application submitted6.4
Holmwood Solar Farmsolar farm19refused on appeal8.1
Boxtedsolar farm20application submitted8.1
Wix Lodgesolar farm18.7operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9104, 0.9938).