Bradwell Wind Farm (Repower) (20 MW)

Bradwell Wind Farm (Repower) is a 20 MW wind farm project in Maldon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 September 2013; the record was last updated on 22 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWwind farm
operationalstatus in REPD
22 January 2014record last updated
Maldoncouncil area

Planning timeline

DateStage
30 March 2006Application submitted
7 July 2006Planning permission granted
1 April 2012Construction started
30 September 2013Operational

Project details

Technology
wind farm
Capacity
20 MW
Status (REPD)
operational
Record last updated
22 January 2014
Operator or applicant
Npower Renewables
Planning authority
Maldon
Planning application reference
06/00291/FUL
Turbines
10
Address (REPD)
Bradwell on Sea, Maldon
Council area (by location)
Maldon
Time to decision
14 weeks
REPD reference
3936

Who decides

ApplicationsMaldonUK
Decided applications (solar, wind, battery)2010,236
Refused11 (55%)19%
Solar refused7 of 1312%
Onshore wind refused2 of 345%
Battery storage refused2 of 416%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dengiesolar farm19approved, not built5.2
Middlewick wind farmwind farm20.7operational7.2
Turncole Wind Farmwind farm17.5operational7.2
Marshes Farmsolar farm25.5approved, not built8.2
Wick Farm (Burnham on Crouch)solar farm5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7098, 0.821).