Bradwell Wind Farm (Repower) (20 MW)
Bradwell Wind Farm (Repower) is a 20 MW wind farm project in Maldon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 September 2013; the record was last updated on 22 January 2014.
20 MWwind farm
operationalstatus in REPD
22 January 2014record last updated
Maldoncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 30 March 2006 | Application submitted |
| 7 July 2006 | Planning permission granted |
| 1 April 2012 | Construction started |
| 30 September 2013 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 20 MW
- Status (REPD)
- operational
- Record last updated
- 22 January 2014
- Operator or applicant
- Npower Renewables
- Planning authority
- Maldon
- Planning application reference
- 06/00291/FUL
- Turbines
- 10
- Address (REPD)
- Bradwell on Sea, Maldon
- Council area (by location)
- Maldon
- Time to decision
- 14 weeks
- REPD reference
- 3936
Who decides
| Applications | Maldon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 20 | 10,236 |
| Refused | 11 (55%) | 19% |
| Solar refused | 7 of 13 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 2 of 4 | 16% |
| Median time from submission to decision | 19.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Dengie | solar farm | 19 | approved, not built | 5.2 |
| Middlewick wind farm | wind farm | 20.7 | operational | 7.2 |
| Turncole Wind Farm | wind farm | 17.5 | operational | 7.2 |
| Marshes Farm | solar farm | 25.5 | approved, not built | 8.2 |
| Wick Farm (Burnham on Crouch) | solar farm | 5 | operational | 9.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7098, 0.821).