Energy Projects Near You

Middlewick wind farm (20.7 MW)

Middlewick wind farm is a 20.7 MW wind farm project in Maldon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 July 2014; the record was last updated on 5 January 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.7 MWwind farm
operationalstatus in REPD
5 January 2015record last updated
Maldoncouncil area

Planning timeline

DateStage
5 January 2010Application submitted
6 August 2010Refused by the planning authority
1 May 2011Planning permission granted
1 May 2011Appeal allowed
4 June 2013Construction started
31 July 2014Operational

Project details

Technology
wind farm
Capacity
20.7 MW
Status (REPD)
operational
Record last updated
5 January 2015
Operator or applicant
Blue Energy (formerly Ridgewind Ltd)
Planning authority
Maldon
Planning application reference
10/00004/FUL
Appeal reference
APP/X1545/A/10/2140423/NWF
Turbines
9
Address (REPD)
Land Between Middlewick Farm And Wraywick Farm, The Marshes, Southminster, Essex
Council area (by location)
Maldon
Time to decision
69 weeks
REPD reference
4662

Who decides

ApplicationsMaldonUK
Decided applications (solar, wind, battery)2010,236
Refused11 (55%)19%
Solar refused7 of 1312%
Onshore wind refused2 of 345%
Battery storage refused2 of 416%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dengiesolar farm19approved, not built2.0
Turncole Wind Farmwind farm17.5operational2.1
Marshes Farmsolar farm25.5approved, not built4.4
Wick Farm (Burnham on Crouch)solar farm5operational5.3
Bradwell Wind Farm (Repower)wind farm20operational7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6631, 0.8925).