Energy Projects Near You

Solar, wind and battery projects near Maldon (CM9)

22 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CM9 (Maldon): 1 is waiting for a planning decision, 9 approved but not yet running, 6 operational. The largest live scheme is Maldon Hall (40 MW battery storage, approved on 13 May 2019, not yet built; REPD status may be out of date), 2.3 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Gunfleet Sands - (Demo) Extension (12 MW, operational), 34.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22projects within 10 km
1awaiting a decision
9approved, not running
6operational

Projects within 10 km of CM9

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Maldon Hallbattery storagebattery storage40approved, not built may be out of dateupdated Dec 2021Sep 2017granted May 2019Dec 2021Maldon2.3
Beckingham Roadsolar farmsolar farm10.7refusedupdated Sep 2014May 2014refused Jul 2014Sep 2014Maldon4.2
Maldon Wycke Solar Farmsolar farmsolar farm25operationalupdated Oct 2024Feb 2022granted Aug 2022Oct 2024Maldon4.8
Little Braxted Solar Parksolar farmsolar farm15appeal withdrawnupdated Jan 2014Jan 2013refused Jun 2013Jan 2014Maldon7.3
Prentice’s Farm- Solar Farmsolar farmsolar farm21approved, not builtupdated Feb 2026Apr 2024granted Sep 2024Feb 2026Maldon7.6
Corporation Farmsolar farmsolar farm5abandonedupdated Mar 2019Aug 2015granted Apr 2017Mar 2019Maldon7.6
Wilkin And Sons, Factory Hill Solar Farmsolar farmsolar farm6.2operationalupdated Mar 2024Dec 2022granted Jun 2023Mar 2024Colchester8.3
Jackletts Farmsolar farmsolar farm10refusedupdated Jul 2014Jul 2013refused Oct 2013Jul 2014Maldon8.5
Land West Of Flambirds Farmsolar farmsolar farm5refusedupdated Dec 2015Aug 2015refused Nov 2015Dec 2015Maldon8.6
Bradwell Wind Farm (Repower)wind farmwind farm20operationalupdated Jan 2014Mar 2006granted Jul 2006Jan 2014Maldon9.1
Highfields Farm (Colchester)solar farmsolar farm12.2operationalupdated Sep 2014Dec 2012granted Sep 2013Sep 2014Colchester9.5
Highfields Farm (Braintree)solar farmsolar farm2.8operationalupdated Sep 2014Dec 2012granted Sep 2013Sep 2014Colchester9.5
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sub Zero And Wolf Limited, The Streetrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Nov 2022Aug 2022granted Oct 2022Nov 2022Maldon0.7
Howbridge Junior School, Dengie Closerooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Braintree7.1
Motus Trucks and Vans, Griggs Wayrooftop solarrooftop solar0.3approved, not builtupdated Feb 2023Dec 2022granted Feb 2023Feb 2023Braintree7.5
Spinks Lane - Micro Energy Facilitybattery storagebattery storage0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Braintree7.7
Colemans Farmsolar farmsolar farm0.3application submitted may be out of dateupdated May 2019May 2019—May 2019Braintree7.8
Cego Limited, Crittall Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Braintree8.3
Church Road Tescorooftop solarrooftop solar0.2approved, not builtupdated Jun 2020Oct 2019granted Nov 2019Jun 2020Colchester8.5
Morrisons Withamrooftop solarrooftop solar0.2operationalupdated Nov 2021Nov 2021granted Mar 2023Nov 2021Braintree8.7
Danbury Outdoors, Well Lanesolar farmsolar farm—application withdrawnupdated Dec 2022Sep 2022—Dec 2022Chelmsford9.4
Verge By Ricksones School, Rickstones Road - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025Braintree9.6

Distance from the average position of the CM9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm12114321.3
Rooftop solar605101
Wind farm100100
Battery storage3030040.4

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Gunfleet Sands - (Demo) Extension12operationalupdated Nov 201734.2
Gunfleet Sands Offshore Wind Scheme108operationalupdated May 201835.8
Gunfleet Sands II64.8operationalupdated Nov 201737.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Maldon decides solar, wind and battery applications

ApplicationsMaldonUK
Decided applications (solar, wind, battery)2010,236
Refused11 (55%)19%
Solar refused7 of 1312%
Onshore wind refused2 of 345%
Battery storage refused2 of 416%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

All projects in Maldon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CM9, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.