Prentice’s Farm- Solar Farm (21 MW)

Prentice’s Farm- Solar Farm is a 21 MW solar farm project in Maldon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 September 2024, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Maldoncouncil area

Planning timeline

DateStage
24 April 2024Application submitted
6 September 2024Planning permission granted
6 September 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
21 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Anglo Renewables
Planning authority
Maldon
Planning application reference
24/00366/FULM
Site area
33.2 ha
Address (REPD)
Sw/O The Warren, Hackmans Lane, Purleigh, Chelmsford
Council area (by location)
Maldon
Time to decision
19 weeks
Contracts for Difference
AR7a
REPD reference
16390

Earlier applications for this site

ApplicationMWSubmittedOutcome
Prentice’s Farm- Solar Farm 23/00807/FULM2515 August 2023refused 1 February 2024

Who decides

ApplicationsMaldonUK
Decided applications (solar, wind, battery)2010,236
Refused11 (55%)19%
Solar refused7 of 1312%
Onshore wind refused2 of 345%
Battery storage refused2 of 416%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Corporation Farmsolar farm5abandoned0.1
Jackletts Farmsolar farm10refused1.6
Land West Of Flambirds Farmsolar farm5refused1.6
Maldon Wycke Solar Farmsolar farm25operational2.9
Maldon Hallbattery storage40approved, not built5.4
St Cleres Hall Pit Solar Arraysolar farm25approved, not built6.2
Hill Farm Solar Park & Battery Storage (Hanningfield Green)solar farm36.7approved, not built6.4
Battlesbridge Bypass, Rettendonbattery storage100refused6.7
Canon Barns Road Solar Photovoltaic Arrays & Battery Storagesolar farm49.9approved, not built7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6896, 0.6255).