Battlesbridge Bypass, Rettendon (100 MW battery storage)

Battlesbridge Bypass, Rettendon is a 100 MW battery storage project in Chelmsford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 30 May 2022; the record was last updated on 14 October 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
refusedstatus in REPD
14 October 2021record last updated
Chelmsfordcouncil area

Planning timeline

DateStage
2 February 2022Application submitted
30 May 2022Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
refused
Record last updated
14 October 2021
Operator or applicant
Pelagic Energy
Planning authority
Chelmsford
Planning application reference
22/00179/FUL
Address (REPD)
W/O Battlesbridge Bypass, Rettendon, Wickford
Council area (by location)
Chelmsford
Time to decision
17 weeks
Name in REPD
Battlesbridge Bypass, Rettendon - Battery Storage
REPD reference
9801

Who decides

ApplicationsChelmsfordUK
Decided applications (solar, wind, battery)1510,236
Refused5 (33%)19%
Solar refused3 of 912%
Battery storage refused2 of 616%
Median time from submission to decision32.3 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Southlands Solar Farm & Battery Storagesolar farm24.6approved, not built2.8
Canon Barns Road Solar Photovoltaic Arrays & Battery Storagesolar farm49.9approved, not built3.8
Canon Barns Road Solar Parksolar farm8approved, not built4.3
Rayleigh Spur Roundabout, Benfleetbattery storage150application submitted4.9
Hill Farm Solar Park & Battery Storage (Hanningfield Green)solar farm36.7approved, not built5.0
Dollymans Storagebattery storage100operational5.0
Land West Of Flambirds Farmsolar farm5refused5.7
Rayleigh Transforming Stationbattery storage10.8permission expired6.0
Fairlawns Farm, Chelmsford Roadbattery storage480approved, not built6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6387, 0.5738).