Fairlawns Farm, Chelmsford Road (480 MW battery storage)

Fairlawns Farm, Chelmsford Road is a 480 MW battery storage project in Rochford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 July 2025, not yet built; the record was last updated on 7 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

480 MWbattery storage
approved, not builtstatus in REPD
7 November 2025record last updated
Rochfordcouncil area

Planning timeline

DateStage
31 July 2024Application submitted
17 July 2025Planning permission granted
17 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
480 MW
Status (REPD)
approved, not built
Record last updated
7 November 2025
Operator or applicant
Gresham House Devco Pipeline
Planning authority
Rochford
Planning application reference
24/00455/FUL
Address (REPD)
Fairlawns Farm, Chelmsford Road, Rayleigh
Council area (by location)
Rochford
Time to decision
50 weeks
Name in REPD
Fairlawns Farm, Chelmsford Road - Battery Energy Storage
REPD reference
16887

Who decides

ApplicationsRochfordUK
Decided applications (solar, wind, battery)1210,236
Refused3 (25%)19%
Solar refused3 of 912%
Battery storage refused0 of 316%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Great Wheatley Road Solar Farmsolar farm30under construction0.9
Rayleigh Transforming Stationbattery storage10.8permission expired1.1
Dollymans Storagebattery storage100operational3.1
Rayleigh Spur Roundabout, Benfleetbattery storage150application submitted5.1
Southlands Solar Farm & Battery Storagesolar farm24.6approved, not built5.5
Battlesbridge Bypass, Rettendonbattery storage100refused6.2
South Fambridge Hall Solar farm & Battery storagesolar farm50under construction7.2
Fambridge Road/Canewdon Roadsolar farm5permission expired7.2
Fambridge Road/Canewdon Roadsolar farm5operational7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5871, 0.6072).