Energy Projects Near You

Maldon Hall (40 MW battery storage)

Maldon Hall is a 40 MW battery storage project in Maldon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 May 2019, not yet built; the record was last updated on 23 December 2021. REPD also records that the planning permission expired on 13 May 2022, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtmay be out of datestatus in REPD
23 December 2021record last updated
Maldoncouncil area

REPD also records that the planning permission expired on 13 May 2022, so the project may not go ahead in this form.

Planning timeline

DateStage
29 September 2017Application submitted
15 December 2017Refused by the planning authority
14 January 2019Appeal lodged
13 May 2019Planning permission granted
13 May 2019Appeal allowed
13 May 2022Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
23 December 2021
Operator or applicant
Green Investment Group
Planning authority
Maldon
Planning application reference
17/01106/FUL
Appeal reference
APP/X1545/W/18/3204562
Address (REPD)
Land North West Of Maldon Hall, Spital Road, Maldon
Council area (by location)
Maldon
Time to decision
84 weeks
REPD reference
7095

Who decides

ApplicationsMaldonUK
Decided applications (solar, wind, battery)2010,236
Refused11 (55%)19%
Solar refused7 of 1312%
Onshore wind refused2 of 345%
Battery storage refused2 of 416%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Maldon Wycke Solar Farmsolar farm25operational2.9
Prentice’s Farm- Solar Farmsolar farm21approved, not built5.4
Corporation Farmsolar farm5abandoned5.4
Beckingham Roadsolar farm10.7refused6.0
Jackletts Farmsolar farm10refused6.3
Land West Of Flambirds Farmsolar farm5refused6.6
Little Braxted Solar Parksolar farm15appeal withdrawn8.1
St Cleres Hall Pit Solar Arraysolar farm25approved, not built8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7293, 0.6712).