Energy Projects Near You

Kentish Flats offshore wind farm

Kentish Flats is a 90 MW offshore wind farm with 30 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 September 2005; the record was last updated on 27 October 2017. Its REPD grid reference is 10 km from the nearest postcode on land (CT6 8EP, Canterbury). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

90 MWoffshore wind farm
operationalstatus in REPD
27 October 2017record last updated
10 km from land (Canterbury)REPD location

Consent timeline

DateStage
15 August 2002Application submitted
1 March 2003Section 36 consent granted (Secretary of State)
1 June 2004Construction started
10 September 2005Operational

Project details

Technology
offshore wind farm
Capacity
90 MW
Turbines
30
Turbine capacity
3 MW
Status (REPD)
operational
Record last updated
27 October 2017
Operator or applicant
Vattenfall
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
CT6 8EP (Canterbury), 9.9 km from the REPD grid reference
Time to decision
28 weeks
REPD reference
2492

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Herne Bay (CT6)11.0
Whitstable (CT5)12.6
Birchington (CT7)17.2
Canterbury (CT2)18.5
Westgate-on-Sea (CT8)19.1
Canterbury (CT1)20.4
Sheerness (ME12)20.5
Canterbury (CT3)22.0
Faversham (ME13)22.2
Margate (CT9)22.2
Southend-on-Sea (SS3)23.0
Ramsgate (CT12)23.1

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Kentish Flats 249.5operational1.5
London Array Phase 2240abandoned3.9
Gunfleet Sands - (Demo) Extension12operational27.8

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (51.4606, 1.0938).