Solar, wind and battery projects near Canterbury (CT2)
32 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CT2 (Canterbury): 2 are waiting for a planning decision, 18 approved but not yet running, 5 operational. The largest live scheme is Woodlands Farm, Calcott Hill (228 MW battery storage, approved on 26 May 2026, not yet built), 5.4 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Kentish Flats 2 (49.5 MW, operational), 17.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CT2
Projects of 1 MW and more (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Parker Steel, Vauxhall Industrial Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Oct 2024 | Nov 2024 | Canterbury | 1.7 |
| Britton Court Farm, Hackington Road Solar Farmsolar farm | solar farm | 38 | approved, not builtupdated Jul 2025 | Sep 2024 | granted Jul 2025 | Jul 2025 | Canterbury | 2.3 |
| Woodlands Farm Solar Parksolar farm | solar farm | 10 | operationalupdated May 2015 | Feb 2014 | granted May 2014 | May 2015 | Canterbury | 4.6 |
| Littlebournesolar farm | solar farm | 17 | operationalupdated Mar 2015 | Oct 2013 | granted Jan 2014 | Mar 2015 | Canterbury | 4.9 |
| Nackington Farm Solar Park- Site Bsolar farm | solar farm | 16.6 | application withdrawnupdated Sep 2014 | Jan 2014 | — | Sep 2014 | Canterbury | 5.1 |
| Nackington Farm Solar Park- Site Csolar farm | solar farm | 12 | application withdrawnupdated Sep 2014 | Jan 2014 | — | Sep 2014 | Canterbury | 5.1 |
| Nackington Farm Solar Park- Site Asolar farm | solar farm | 11 | application withdrawnupdated Sep 2014 | Jan 2014 | — | Sep 2014 | Canterbury | 5.2 |
| Woodlands Farm, Calcott Hillbattery storage | battery storage | 228 | approved, not builtupdated Jun 2026 | Mar 2025 | granted May 2026 | Jun 2026 | Canterbury | 5.4 |
| Thanet Way, Herne Bay Solar Farmsolar farm | solar farm | 20 | permission expiredupdated Nov 2021 | Oct 2020 | granted Mar 2021 | Nov 2021 | Canterbury | 6.4 |
| Owls Hatch Roadsolar farm | solar farm | 48 | operationalupdated Oct 2016 | Aug 2014 | granted Jan 2015 | Oct 2016 | Canterbury | 6.5 |
| Owls Hatch Road, Thanet Waybattery storage | battery storage | 50 | approved, not builtupdated Jul 2025 | Dec 2024 | granted Jul 2025 | Jul 2025 | Canterbury | 6.6 |
| Molehill Farmsolar farm | solar farm | 18 | operationalupdated Apr 2015 | Oct 2013 | granted Feb 2014 | Apr 2015 | Canterbury | 7.0 |
| Marley Lane Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | refusedupdated Jan 2026 | Mar 2025 | refused Dec 2025 | Jan 2026 | Canterbury | 8.4 |
| North Court Farm, Chilham Solar Farmsolar farm | solar farm | 44 | refused on appealupdated May 2024 | Oct 2022 | refused Apr 2024 | May 2024 | Ashford | 8.6 |
Smaller schemes under 1 MW, mostly rooftop solar (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| University Of Kent, Templeman Libraryrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2025 | Nov 2024 | granted Dec 2024 | Jan 2025 | Canterbury | 0.9 |
| Kings School Recreation Centre, St Stephens Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Apr 2025 | granted Jul 2025 | Aug 2025 | Canterbury | 1.0 |
| Britton Court Farm, Hackington Roadbattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Sep 2024 | granted Jul 2025 | Jul 2025 | Canterbury | 2.3 |
| Morrisons, Ten Perch Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Canterbury | 2.8 |
| Kent And Canterbury Hospital, Ethelbert Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Canterbury | 3.1 |
| Kent Canterbury Hospital, Ethelbert Roadrooftop solar | rooftop solar | 0.8 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | Canterbury | 3.1 |
| Amery Court Farmrooftop solar | rooftop solar | — | application submitted may be out of dateupdated Oct 2021 | Oct 2021 | — | Oct 2021 | Canterbury | 3.2 |
| Howfield Farm, Howfield Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Oct 2025 | Dec 2025 | Canterbury | 4.6 |
| Mansfield Farm, Bridgerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Feb 2025 | granted Apr 2025 | Jun 2025 | Canterbury | 6.4 |
| Mansfield Farms, Nickle Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Canterbury | 6.5 |
| Markerstudy Business Park, Wraik Hill - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Canterbury | 6.8 |
| Nickle Farm, Nickle Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2024 | Sep 2024 | granted Oct 2024 | Oct 2024 | Canterbury | 6.8 |
| Nickle Farm, Mansfield Farmsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Apr 2025 | granted Jul 2025 | Aug 2025 | Canterbury | 6.8 |
| Nickle Farm, Nickle Lanerooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Canterbury | 6.8 |
| Mansfield Farms, Nickle Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2023 | Jul 2022 | granted Sep 2022 | Jan 2023 | Canterbury | 6.8 |
| Nickle Farmrooftop solar | rooftop solar | 0.3 | operationalupdated Jun 2021 | Feb 2021 | granted Dec 2021 | Jun 2021 | Canterbury | 6.8 |
| Swalecliffe Community Primary School, Bridgefield Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Canterbury | 7.7 |
| Marley Lane Solar Farm & Battery Storagebattery storage | battery storage | — | refusedupdated Jan 2026 | Mar 2025 | refused Dec 2025 | Jan 2026 | Canterbury | 8.4 |
Distance from the average position of the CT2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 11 | 0 | 1 | 4 | 2 | 38 |
| Rooftop solar | 16 | 2 | 13 | 1 | 0 | 5.9 |
| Battery storage | 5 | 0 | 4 | 0 | 1 | 278 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Kentish Flats 2 | 49.5 | operationalupdated Jun 2016 | 17.3 |
| Kentish Flats | 90 | operationalupdated Oct 2017 | 18.5 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Canterbury decides solar, wind and battery applications
| Applications | Canterbury | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 26 | 10,236 |
| Refused | 2 (8%) | 19% |
| Solar refused | 1 of 21 | 12% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 12.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CT2, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.