Woodlands Farm Solar Park (10 MW)

Woodlands Farm Solar Park is a 10 MW solar farm project in Canterbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 14 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
14 May 2015record last updated
Canterburycouncil area

Planning timeline

DateStage
18 February 2014Application submitted
7 May 2014Planning permission granted
24 November 2014Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
14 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Canterbury
Planning application reference
CA//14/00169
Site area
21.0 ha
Address (REPD)
Woodlands Farm, Calcott Hill, Sturry
Council area (by location)
Canterbury
Time to decision
11 weeks
REPD reference
1516

Who decides

ApplicationsCanterburyUK
Decided applications (solar, wind, battery)2610,236
Refused2 (8%)19%
Solar refused1 of 2112%
Battery storage refused1 of 516%
Median time from submission to decision12.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Woodlands Farm, Calcott Hillbattery storage228approved, not built0.8
Owls Hatch Roadsolar farm48operational3.4
Owls Hatch Road, Thanet Waybattery storage50approved, not built3.7
Thanet Way, Herne Bay Solar Farmsolar farm20permission expired3.8
Britton Court Farm, Hackington Road Solar Farmsolar farm38approved, not built3.8
Marley Lane Solar Farm & Battery Storagesolar farm49.9refused4.4
Molehill Farmsolar farm18operational4.4
Littlebournesolar farm17operational5.9
Nackington Farm Solar Park- Site Asolar farm11application withdrawn8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3252, 1.124).