Nackington Farm Solar Park- Site A (11 MW)
Nackington Farm Solar Park- Site A is an 11 MW solar farm project in Canterbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 1 September 2014; the record was last updated on 16 September 2014.
11 MWsolar farm
application withdrawnstatus in REPD
16 September 2014record last updated
Canterburycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 31 January 2014 | Application submitted |
| 1 September 2014 | Application withdrawn |
Project details
- Technology
- solar farm
- Capacity
- 11 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 16 September 2014
- Operator or applicant
- Green Energy UK Direct Ltd
- Planning authority
- Canterbury
- Planning application reference
- CA//14/00087
- Site area
- 20.7 ha
- Address (REPD)
- Nackington Farm, Nackington Road, Lower Hardres
- Council area (by location)
- Canterbury
- REPD reference
- 2303
Who decides
| Applications | Canterbury | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 26 | 10,236 |
| Refused | 2 (8%) | 19% |
| Solar refused | 1 of 21 | 12% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 12.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Nackington Farm Solar Park- Site C | solar farm | 12 | application withdrawn | 0.4 |
| Nackington Farm Solar Park- Site B | solar farm | 16.6 | application withdrawn | 0.4 |
| Littlebourne | solar farm | 17 | operational | 4.6 |
| Britton Court Farm, Hackington Road Solar Farm | solar farm | 38 | approved, not built | 7.5 |
| North Court Farm, Chilham Solar Farm | solar farm | 44 | refused on appeal | 8.4 |
| Chapmans Hill | solar | 7 | application withdrawn | 8.8 |
| Woodlands Farm Solar Park | solar farm | 10 | operational | 8.9 |
| Snowdown Colliery | solar farm | 5 | permission expired | 9.6 |
| Woodlands Farm, Calcott Hill | battery storage | 228 | approved, not built | 9.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2479, 1.0926).